1
Planning
12 days Tue 28.09.04 Wed 13.10.04   100%
2
Project Proposal
11 days Tue 28.09.04 Tue 12.10.04   100%
3
Milestone
0 days Wed 13.10.04 Wed 13.10.04   100%
4
RequirementsAnalysis
32 days Thu 14.10.04 Wed 24.11.04   100%
5
Specification Research
5 days Thu 14.10.04 Tue 19.10.04   100%
6
Web Questionnaire
29 days Thu 14.10.04 Fri 19.11.04   100%
7
Requirements Specification
18 days Mon 01.11.04 Tue 23.11.04   100%
8
Milestone
0 days Wed 24.11.04 Wed 24.11.04   100%
9
Initial Design
10 days Thu 25.11.04 Wed 08.12.04   100%
10
Design Drafts for Modules
4 days Thu 25.11.04 Tue 30.11.04   100%
11
Initial Design Specification
7 days Mon 29.11.04 Tue 07.12.04   100%
12
Milestone
0 days Wed 08.12.04 Wed 08.12.04   100%
13
Detailed Design
24 days Thu 09.12.04 Mon 10.01.05   100%
14
Draft Design Specification
6 days Thu 09.12.04 Thu 16.12.04   100%
15
Object Oriented Architectural & Procedural Design
13 days Fri 10.12.04 Mon 27.12.04   100%
16
Complete Class Diagrams
10 days Wed 22.12.04 Mon 03.01.05   100%
17
Hardware Design
22 days Fri 10.12.04 Fri 07.01.05   100%
18
Interface Design
5 days Fri 31.12.04 Thu 06.01.05   100%
19
Test Provisions
19 days Thu 16.12.04 Mon 10.01.05   100%
20
Design Specification
6 days Mon 03.01.05 Mon 10.01.05   100%
21
Milestone
0 days Mon 10.01.05 Mon 10.01.05   100%
22
Pre - Implementation
23 days Mon 20.12.04 Wed 19.01.05   100%
23
Prototype
23 days Mon 20.12.04 Tue 18.01.05   100%
24
Milestone
0 days Wed 19.01.05 Wed 19.01.05   100%
25
Implementation
100 days? Tue 01.02.05 Tue 14.06.05   100%
26
Prototype review
5 days Tue 01.02.05 Mon 07.02.05   100%
27
Implementation Initials
8 days Tue 01.02.05 Thu 10.02.05   100%
28
System Database Modules
4 days? Sun 13.03.05 Wed 16.03.05   100%
29
DB Tables
4 days Sun 13.03.05 Wed 16.03.05 Bilal;Okan;Kerim 100%
30
DB Queries
4 days? Sun 13.03.05 Wed 16.03.05 Bilal;Okan;Kerim 100%
31
Module
79 days? Tue 08.02.05 Thu 26.05.05   52%
32
Wireless Communication Modules
60 days? Tue 08.02.05 Thu 28.04.05 Özkan;Kerim 10%
33
Wireless Communication Modules
4 days Tue 03.05.05 Fri 06.05.05 Bilal;Okan 100%
34
Card Implementation
66 days Mon 14.02.05 Thu 12.05.05   100%
35
Modifying PIC program, circuit design,etc.
52 days Mon 14.02.05 Fri 22.04.05   100%
36
Modifying PIC program for the first development snapshot
6 days Fri 11.03.05 Thu 17.03.05 Okan;Bilal 100%
37
Modifying PIC program & circuit design for Regular Demo (I)
10 days Fri 18.03.05 Thu 31.03.05 Okan;Bilal 100%
38
Modifying PIC program & circuit design for Regular Demo (II)
10 days Fri 01.04.05 Thu 14.04.05 Okan;Bilal 100%
39
Modifying PIC program & circuit design for Regular Demo (III)
11 days Fri 15.04.05 Thu 28.04.05 Okan;Bilal 100%
40
Modifying PIC program & circuit design for Regular Demo (IV)
10 days Fri 29.04.05 Thu 12.05.05 Okan;Bilal 100%
41
Main-Board Program
61 days? Tue 15.02.05 Fri 06.05.05   30%
42
Modifying mainboard program
48 days? Tue 15.02.05 Tue 19.04.05   0%
43
Interface mainboard program with MySQL for the first development snapshot
6 days Fri 11.03.05 Thu 17.03.05 Özkan;Kerim 100%
44
Integration mainboard program with MySQL for Regular Demo (III)
31 days Fri 18.03.05 Thu 28.04.05 Özkan;Kerim 10%
45
Interface to the C4 Control Card for the first development snapshot
6 days Fri 11.03.05 Thu 17.03.05 Okan;Bilal 100%
46
Correction of the interface(from first development snapshot) to the C4 Control Card for Regular Demo(I)
10 days Fri 18.03.05 Thu 31.03.05 Okan 100%
47
Modifying OS (Linux that bootable from flash disk) for using MySQL and Wireless for Regular Demo (III)
31 days Fri 18.03.05 Thu 28.04.05 Özkan;Kerim 3%
48
Modifying OS (Linux that bootable from flash disk) and Wireless for First Release
4 days Tue 03.05.05 Fri 06.05.05 Okan;Bilal 100%
49
GUI Implementation
43 days Mon 07.03.05 Mon 02.05.05   100%
50
Implementing User Interfaces with PHP and MySQL
31 days Mon 07.03.05 Fri 15.04.05   100%
51
Designing and Implementing first level of main menu of the GUIs for Regular Demo (I)
10 days Fri 18.03.05 Thu 31.03.05 Bilal 100%
52
Designing and Implementing the GUIs for Regular Demo (II)
10 days Fri 01.04.05 Thu 14.04.05 Bilal 100%
53
Designing and Implementing the GUIs for Regular Demo (III)
11 days Fri 15.04.05 Thu 28.04.05 Bilal;Okan 100%
54
Designing and Implementing the GUIs for First Release
6 days Mon 25.04.05 Mon 02.05.05 Bilal;Okan 100%
55
Administrator Program
47 days Mon 07.03.05 Fri 06.05.05   100%
56
Integration of admin program database with main board program by means of network
32 days Mon 07.03.05 Sat 16.04.05   100%
57
Implementing main base of admin program (network communication with main boards) for Regular Demo (II)
20 days Fri 18.03.05 Thu 14.04.05 Okan;Kerim 100%
58
Implementing admin program (network communication with main boards) for Regular Demo (III)
11 days Fri 15.04.05 Thu 28.04.05 Okan;Bilal 100%
59
Implementing admin program (network communication with main boards) for First Release
10 days Mon 25.04.05 Fri 06.05.05 Okan;Bilal 100%
60
First development shapshot-Milestone
0 days Thu 17.03.05 Thu 17.03.05   100%
61
Regular Demo (I)
0 days Thu 31.03.05 Thu 31.03.05   100%
62
Regular Demo (II)
0 days Thu 14.04.05 Thu 14.04.05   100%
63
Regular Demo (III)
0 days Thu 28.04.05 Thu 28.04.05   100%
64
Regular Demo (IV)
0 days Thu 12.05.05 Thu 12.05.05   100%
65
Regular Demo (V)
0 days Thu 26.05.05 Thu 26.05.05   100%
66
Performance Improvement
15 days Mon 25.04.05 Fri 13.05.05 Okan;Bilal 100%
67
Tests
28 days Mon 02.05.05 Tue 07.06.05 Okan;Bilal 100%
68
First version Release - Milestone
0 days Mon 02.05.05 Mon 02.05.05 Okan;Bilal 100%
69
Implementation (final)
10 days Tue 31.05.05 Sun 12.06.05 Okan;Bilal 100%
70
Final Demo of the project
2 days Mon 13.06.05 Tue 14.06.05   90%
71
Documentation
97 days Wed 02.02.05 Sun 12.06.05   100%
72
Web Page of the project
94 days Wed 02.02.05 Wed 08.06.05 Bilal 100%
73
Living Schedule
78 days Mon 21.02.05 Fri 03.06.05 Okan 100%
74
Peer Evaluation - Design Review
4 days Tue 01.03.05 Fri 04.03.05 Whole Team 100%
75
Configuration Management Plan
5 days Tue 08.03.05 Sun 13.03.05 Whole Team 100%
76
Test Documentation
6 days Fri 29.04.05 Fri 06.05.05 Kerim;Özkan 100%
77
Compilation manual
10 days Mon 30.05.05 Fri 10.06.05 Okan;Bilal 100%
78
User and administration manual
10 days Fri 27.05.05 Fri 10.06.05 Kerim;Özkan 100%
79
Developers guide
10 days Mon 30.05.05 Fri 10.06.05 Okan;Bilal 100%
80
Installation manual
10 days Mon 30.05.05 Sun 12.06.05 Okan;Bilal 100%
81
Milestone
0 days Wed 08.06.05 Wed 08.06.05   100%
82
Customer Evaluation
2 days? Sun 12.06.05 Mon 13.06.05   0%
83
Feedback
2 days? Sun 12.06.05 Mon 13.06.05   0%
84
Milestone
0 days Mon 13.06.05 Mon 13.06.05   0%