Project Start Date: Tue 28.09.04
Project Finish Date: Tue 14.06.05
(Last updated at 12.06.2005) FINAL RELEASE
ID | Name
|
Duration | Start_Date | Finish | Assigned To | Percent Work Complete |
---|---|---|---|---|---|---|
1 | Planning
|
12 days | Tue 28.09.04 | Wed 13.10.04 | 100% | |
2 | Project Proposal
|
11 days | Tue 28.09.04 | Tue 12.10.04 | 100% | |
3 | Milestone
|
0 days | Wed 13.10.04 | Wed 13.10.04 | 100% | |
4 | RequirementsAnalysis
|
32 days | Thu 14.10.04 | Wed 24.11.04 | 100% | |
5 | Specification Research
|
5 days | Thu 14.10.04 | Tue 19.10.04 | 100% | |
6 | Web Questionnaire
|
29 days | Thu 14.10.04 | Fri 19.11.04 | 100% | |
7 | Requirements Specification
|
18 days | Mon 01.11.04 | Tue 23.11.04 | 100% | |
8 | Milestone
|
0 days | Wed 24.11.04 | Wed 24.11.04 | 100% | |
9 | Initial Design
|
10 days | Thu 25.11.04 | Wed 08.12.04 | 100% | |
10 | Design Drafts for Modules
|
4 days | Thu 25.11.04 | Tue 30.11.04 | 100% | |
11 | Initial Design Specification
|
7 days | Mon 29.11.04 | Tue 07.12.04 | 100% | |
12 | Milestone
|
0 days | Wed 08.12.04 | Wed 08.12.04 | 100% | |
13 | Detailed Design
|
24 days | Thu 09.12.04 | Mon 10.01.05 | 100% | |
14 | Draft Design Specification
|
6 days | Thu 09.12.04 | Thu 16.12.04 | 100% | |
15 | Object Oriented Architectural &
Procedural Design
|
13 days | Fri 10.12.04 | Mon 27.12.04 | 100% | |
16 | Complete Class Diagrams
|
10 days | Wed 22.12.04 | Mon 03.01.05 | 100% | |
17 | Hardware Design
|
22 days | Fri 10.12.04 | Fri 07.01.05 | 100% | |
18 | Interface Design
|
5 days | Fri 31.12.04 | Thu 06.01.05 | 100% | |
19 | Test Provisions
|
19 days | Thu 16.12.04 | Mon 10.01.05 | 100% | |
20 | Design Specification
|
6 days | Mon 03.01.05 | Mon 10.01.05 | 100% | |
21 | Milestone
|
0 days | Mon 10.01.05 | Mon 10.01.05 | 100% | |
22 | Pre - Implementation
|
23 days | Mon 20.12.04 | Wed 19.01.05 | 100% | |
23 | Prototype
|
23 days | Mon 20.12.04 | Tue 18.01.05 | 100% | |
24 | Milestone
|
0 days | Wed 19.01.05 | Wed 19.01.05 | 100% | |
25 | Implementation
|
100 days? | Tue 01.02.05 | Tue 14.06.05 | 100% | |
26 | Prototype review
|
5 days | Tue 01.02.05 | Mon 07.02.05 | 100% | |
27 | Implementation Initials
|
8 days | Tue 01.02.05 | Thu 10.02.05 | 100% | |
28 | System Database Modules
|
4 days? | Sun 13.03.05 | Wed 16.03.05 | 100% | |
29 | DB Tables
|
4 days | Sun 13.03.05 | Wed 16.03.05 | Bilal;Okan;Kerim | 100% |
30 | DB Queries
|
4 days? | Sun 13.03.05 | Wed 16.03.05 | Bilal;Okan;Kerim | 100% |
31 | Module
|
79 days? | Tue 08.02.05 | Thu 26.05.05 | 52% | |
32 | Wireless Communication Modules
|
60 days? | Tue 08.02.05 | Thu 28.04.05 | Özkan;Kerim | 10% |
33 | Wireless Communication Modules
|
4 days | Tue 03.05.05 | Fri 06.05.05 | Bilal;Okan | 100% |
34 | Card Implementation
|
66 days | Mon 14.02.05 | Thu 12.05.05 | 100% | |
35 | Modifying PIC program, circuit
design,etc.
|
52 days | Mon 14.02.05 | Fri 22.04.05 | 100% | |
36 | Modifying PIC program for the first
development snapshot
|
6 days | Fri 11.03.05 | Thu 17.03.05 | Okan;Bilal | 100% |
37 | Modifying PIC program & circuit
design for Regular Demo (I)
|
10 days | Fri 18.03.05 | Thu 31.03.05 | Okan;Bilal | 100% |
38 | Modifying PIC program & circuit
design for Regular Demo (II)
|
10 days | Fri 01.04.05 | Thu 14.04.05 | Okan;Bilal | 100% |
39 | Modifying PIC program & circuit
design for Regular Demo (III)
|
11 days | Fri 15.04.05 | Thu 28.04.05 | Okan;Bilal | 100% |
40 | Modifying PIC program & circuit
design for Regular Demo (IV)
|
10 days | Fri 29.04.05 | Thu 12.05.05 | Okan;Bilal | 100% |
41 | Main-Board Program
|
61 days? | Tue 15.02.05 | Fri 06.05.05 | 30% | |
42 | Modifying mainboard program
|
48 days? | Tue 15.02.05 | Tue 19.04.05 | 0% | |
43 | Interface mainboard program with MySQL
for the first development snapshot
|
6 days | Fri 11.03.05 | Thu 17.03.05 | Özkan;Kerim | 100% |
44 | Integration mainboard program with MySQL
for Regular Demo (III)
|
31 days | Fri 18.03.05 | Thu 28.04.05 | Özkan;Kerim | 10% |
45 | Interface to the C4 Control Card for the
first development snapshot
|
6 days | Fri 11.03.05 | Thu 17.03.05 | Okan;Bilal | 100% |
46 | Correction of the interface(from first
development snapshot) to the C4 Control Card for Regular Demo(I)
|
10 days | Fri 18.03.05 | Thu 31.03.05 | Okan | 100% |
47 | Modifying OS (Linux that bootable from
flash disk) for using MySQL and Wireless for Regular Demo (III)
|
31 days | Fri 18.03.05 | Thu 28.04.05 | Özkan;Kerim | 3% |
48 | Modifying OS (Linux that bootable from
flash disk) and Wireless for First Release
|
4 days | Tue 03.05.05 | Fri 06.05.05 | Okan;Bilal | 100% |
49 | GUI Implementation
|
43 days | Mon 07.03.05 | Mon 02.05.05 | 100% | |
50 | Implementing User Interfaces with PHP
and MySQL
|
31 days | Mon 07.03.05 | Fri 15.04.05 | 100% | |
51 | Designing and Implementing first level
of main menu of the GUIs for Regular Demo (I)
|
10 days | Fri 18.03.05 | Thu 31.03.05 | Bilal | 100% |
52 | Designing and Implementing the GUIs for
Regular Demo (II)
|
10 days | Fri 01.04.05 | Thu 14.04.05 | Bilal | 100% |
53 | Designing and Implementing the GUIs for
Regular Demo (III)
|
11 days | Fri 15.04.05 | Thu 28.04.05 | Bilal;Okan | 100% |
54 | Designing and Implementing the GUIs for
First Release
|
6 days | Mon 25.04.05 | Mon 02.05.05 | Bilal;Okan | 100% |
55 | Administrator Program
|
47 days | Mon 07.03.05 | Fri 06.05.05 | 100% | |
56 | Integration of admin program database
with main board program by means of network
|
32 days | Mon 07.03.05 | Sat 16.04.05 | 100% | |
57 | Implementing main base of admin program
(network communication with main boards) for Regular Demo (II)
|
20 days | Fri 18.03.05 | Thu 14.04.05 | Okan;Kerim | 100% |
58 | Implementing admin program (network
communication with main boards) for Regular Demo (III)
|
11 days | Fri 15.04.05 | Thu 28.04.05 | Okan;Bilal | 100% |
59 | Implementing admin program (network
communication with main boards) for First Release
|
10 days | Mon 25.04.05 | Fri 06.05.05 | Okan;Bilal | 100% |
60 | First development shapshot-Milestone
|
0 days | Thu 17.03.05 | Thu 17.03.05 | 100% | |
61 | Regular Demo (I)
|
0 days | Thu 31.03.05 | Thu 31.03.05 | 100% | |
62 | Regular Demo (II)
|
0 days | Thu 14.04.05 | Thu 14.04.05 | 100% | |
63 | Regular Demo (III)
|
0 days | Thu 28.04.05 | Thu 28.04.05 | 100% | |
64 | Regular Demo (IV)
|
0 days | Thu 12.05.05 | Thu 12.05.05 | 100% | |
65 | Regular Demo (V)
|
0 days | Thu 26.05.05 | Thu 26.05.05 | 100% | |
66 | Performance Improvement
|
15 days | Mon 25.04.05 | Fri 13.05.05 | Okan;Bilal | 100% |
67 | Tests
|
28 days | Mon 02.05.05 | Tue 07.06.05 | Okan;Bilal | 100% |
68 | First version Release - Milestone
|
0 days | Mon 02.05.05 | Mon 02.05.05 | Okan;Bilal | 100% |
69 | Implementation (final)
|
10 days | Tue 31.05.05 | Sun 12.06.05 | Okan;Bilal | 100% |
70 | Final Demo of the project
|
2 days | Mon 13.06.05 | Tue 14.06.05 | 90% | |
71 | Documentation
|
97 days | Wed 02.02.05 | Sun 12.06.05 | 100% | |
72 | Web Page of the project
|
94 days | Wed 02.02.05 | Wed 08.06.05 | Bilal | 100% |
73 | Living Schedule
|
78 days | Mon 21.02.05 | Fri 03.06.05 | Okan | 100% |
74 | Peer Evaluation - Design
Review
|
4 days | Tue 01.03.05 | Fri 04.03.05 | Whole Team | 100% |
75 | Configuration Management Plan
|
5 days | Tue 08.03.05 | Sun 13.03.05 | Whole Team | 100% |
76 | Test Documentation
|
6 days | Fri 29.04.05 | Fri 06.05.05 | Kerim;Özkan | 100% |
77 | Compilation manual
|
10 days | Mon 30.05.05 | Fri 10.06.05 | Okan;Bilal | 100% |
78 | User and administration manual
|
10 days | Fri 27.05.05 | Fri 10.06.05 | Kerim;Özkan | 100% |
79 | Developers guide
|
10 days | Mon 30.05.05 | Fri 10.06.05 | Okan;Bilal | 100% |
80 | Installation manual
|
10 days | Mon 30.05.05 | Sun 12.06.05 | Okan;Bilal | 100% |
81 | Milestone
|
0 days | Wed 08.06.05 | Wed 08.06.05 | 100% | |
82 | Customer Evaluation
|
2 days? | Sun 12.06.05 | Mon 13.06.05 | 0% | |
83 | Feedback
|
2 days? | Sun 12.06.05 | Mon 13.06.05 | 0% | |
84 | Milestone
|
0 days | Mon 13.06.05 | Mon 13.06.05 | 0% |