Work Package ID

Work Package Name Estimated Duration Start Date Due Date Assigned To Status
1 Phase 1: CM Plan & Development Snapshot 29 days Feb. 21st Mar. 21st Detailed Below Completed
1.1 Creation of JSP pages for login & main frame 7 days Feb. 21st Feb. 28th Firat & Mehmet Completed
1.2 Creation of JSP pages for Administration Tab (limited for dev. snapshot) 7 days Feb. 21st Feb. 28th Firat & Mehmet Completed
1.3 Creation of JSP pages for My Office Tab (limited for dev. snapshot) 7 days Mar. 1st Mar. 8th Firat & Mehmet Completed
1.4 Creation of JSP pages for Project Tab (limited for dev. snapshot) 7 days Mar. 1st Mar. 8th Firat & Mehmet Completed
1.5 Creation of Database Tables 3 days Feb. 21st Feb. 24th Tuncay & Dogan Completed
1.6 Creation of Classes that interact with the Database (limited for dev. snapshot) 10 days Feb 25th Mar. 7th Tuncay & Dogan Completed
1.7 Creation of Java Beans for all forms (limited for dev. snapshot) 15 days Mar. 1st Mar. 16th Tuncay & Dogan Completed
1.8 Creation of Configuration Management Plan 3 days Mar. 9th Mar. 12th Mehmet & Firat Completed
1.9 Creation of Servlets for Company Creation & Login 7 days Mar. 12th Mar. 19th Mehmet Completed
1.10 Creation of Servlets for Task Creation & Assignment 7 days Mar. 12th Mar. 19th Firat Completed
1.11 Creation of Servlets for Project Creation & Assignment 7 days Mar. 11th Mar. 18th Dogan Completed
1.12 Creation of Servlets for User Creation & Management 7 days Mar. 11th Mar. 18th Tuncay Completed
1.13 Integration & Last Review for Development Snapshot 2 days Mar. 19th Mar. 21st Whole Team Completed
END OF PHASE 1
2 Phase 2: First Release and Test Specifications 48 days Mar. 22nd May 9th Detailed Below Completed
2.1 Review of User Interfaces 7 days Mar. 22nd Mar. 29th Firat & Mehmet Completed
2.2 Client-Side Error Checking 7 days Mar. 22nd Mar. 29th Dogan Completed
2.3 Server-Side Error Checking 7 days Mar. 22nd Mar. 29th Tuncay Completed
2.4 Completion of JSP pages for Administration Tab 20 days Mar. 22nd Apr. 11th Firat & Mehmet Completed
2.5 Completion of JSP pages for My Office Tab 20 days Mar. 22nd Apr. 11th Firat & Mehmet Completed
2.6 Completion of JSP pages for Project Tab 20 days Mar. 22nd Apr. 11th Firat & Mehmet Completed
2.7 Completion of Classes that interact with the Database 20 days Mar. 22nd Apr. 11th Dogan & Tuncay Completed
2.8 Completion of Java Beans for all forms 20 days Mar. 22nd Apr. 11th Dogan & Tuncay Completed
2.9 Creation of Servlets for Meeting Arrangement Module 15 days Apr. 12th Apr. 27th Tuncay & Mehmet Completed
2.10 Creation of Servlets for Notification Module 15 days Apr. 12th Apr. 27th Firat Completed
2.11 Creation of Servlets for Resource Management 15 days Apr. 12th Apr 27th Dogan Completed
2.12 Creation of Test Specifications 7 days Apr. 28th May 5th Every team member will prepare the test specs for the modules he implemented Completed
2.13 Integration & Last Review for First Release 7 days May 2nd May 9th Whole team Completed
END OF PHASE 2
3 Phase 3: Final Product & Documentation 40 days May 10th June 18th Detailed Below Completed
3.1 Creation of Servlets for Report Generation 15 days May 10th May 24th Dogan Completed
3.2 Creation of Servlets for Statistics Generation 15 days May 10th May 24th Firat Completed
3.3 Creation of Servlets for Gantt Chart Interaction 15 days May 10th May 24th Tuncay Completed
3.4 Creation of Servlets for Task Dependency 15 days May 10th May 24th Mehmet Completed
3.5 Creation of Quick Links 5 days May 10th May 15th Firat Completed
3.6 Creation of User Manual 8 days May 25th June 2nd Tuncay & Firat Completed
3.7 Creation of Installation Manual 8 days May 25th June 2nd Mehmet Completed
3.8 Creation of Release Notes & Software Specification 8 days May 25th June 2nd Dogan Completed
3.9 Integration 3 days June 1st June 4th Whole Team Completed
3.10 Testing 10 days June 2nd June 11th Whole Team Completed
3.11 Last Review 7 days June 11th June 18th Whole Team Completed
END OF PHASE 3