Work Package ID |
Work Package Name | Estimated Duration | Start Date | Due Date | Assigned To | Status |
1 | Phase 1: CM Plan & Development Snapshot | 29 days | Feb. 21st | Mar. 21st | Detailed Below | Completed |
1.1 | Creation of JSP pages for login & main frame | 7 days | Feb. 21st | Feb. 28th | Firat & Mehmet | Completed |
1.2 | Creation of JSP pages for Administration Tab (limited for dev. snapshot) | 7 days | Feb. 21st | Feb. 28th | Firat & Mehmet | Completed |
1.3 | Creation of JSP pages for My Office Tab (limited for dev. snapshot) | 7 days | Mar. 1st | Mar. 8th | Firat & Mehmet | Completed |
1.4 | Creation of JSP pages for Project Tab (limited for dev. snapshot) | 7 days | Mar. 1st | Mar. 8th | Firat & Mehmet | Completed |
1.5 | Creation of Database Tables | 3 days | Feb. 21st | Feb. 24th | Tuncay & Dogan | Completed |
1.6 | Creation of Classes that interact with the Database (limited for dev. snapshot) | 10 days | Feb 25th | Mar. 7th | Tuncay & Dogan | Completed |
1.7 | Creation of Java Beans for all forms (limited for dev. snapshot) | 15 days | Mar. 1st | Mar. 16th | Tuncay & Dogan | Completed |
1.8 | Creation of Configuration Management Plan | 3 days | Mar. 9th | Mar. 12th | Mehmet & Firat | Completed |
1.9 | Creation of Servlets for Company Creation & Login | 7 days | Mar. 12th | Mar. 19th | Mehmet | Completed |
1.10 | Creation of Servlets for Task Creation & Assignment | 7 days | Mar. 12th | Mar. 19th | Firat | Completed |
1.11 | Creation of Servlets for Project Creation & Assignment | 7 days | Mar. 11th | Mar. 18th | Dogan | Completed |
1.12 | Creation of Servlets for User Creation & Management | 7 days | Mar. 11th | Mar. 18th | Tuncay | Completed |
1.13 | Integration & Last Review for Development Snapshot | 2 days | Mar. 19th | Mar. 21st | Whole Team | Completed |
END OF PHASE 1 | ||||||
2 | Phase 2: First Release and Test Specifications | 48 days | Mar. 22nd | May 9th | Detailed Below | Completed |
2.1 | Review of User Interfaces | 7 days | Mar. 22nd | Mar. 29th | Firat & Mehmet | Completed |
2.2 | Client-Side Error Checking | 7 days | Mar. 22nd | Mar. 29th | Dogan | Completed |
2.3 | Server-Side Error Checking | 7 days | Mar. 22nd | Mar. 29th | Tuncay | Completed |
2.4 | Completion of JSP pages for Administration Tab | 20 days | Mar. 22nd | Apr. 11th | Firat & Mehmet | Completed |
2.5 | Completion of JSP pages for My Office Tab | 20 days | Mar. 22nd | Apr. 11th | Firat & Mehmet | Completed |
2.6 | Completion of JSP pages for Project Tab | 20 days | Mar. 22nd | Apr. 11th | Firat & Mehmet | Completed |
2.7 | Completion of Classes that interact with the Database | 20 days | Mar. 22nd | Apr. 11th | Dogan & Tuncay | Completed |
2.8 | Completion of Java Beans for all forms | 20 days | Mar. 22nd | Apr. 11th | Dogan & Tuncay | Completed |
2.9 | Creation of Servlets for Meeting Arrangement Module | 15 days | Apr. 12th | Apr. 27th | Tuncay & Mehmet | Completed |
2.10 | Creation of Servlets for Notification Module | 15 days | Apr. 12th | Apr. 27th | Firat | Completed |
2.11 | Creation of Servlets for Resource Management | 15 days | Apr. 12th | Apr 27th | Dogan | Completed |
2.12 | Creation of Test Specifications | 7 days | Apr. 28th | May 5th | Every team member will prepare the test specs for the modules he implemented | Completed |
2.13 | Integration & Last Review for First Release | 7 days | May 2nd | May 9th | Whole team | Completed |
END OF PHASE 2 | ||||||
3 | Phase 3: Final Product & Documentation | 40 days | May 10th | June 18th | Detailed Below | Completed |
3.1 | Creation of Servlets for Report Generation | 15 days | May 10th | May 24th | Dogan | Completed |
3.2 | Creation of Servlets for Statistics Generation | 15 days | May 10th | May 24th | Firat | Completed |
3.3 | Creation of Servlets for Gantt Chart Interaction | 15 days | May 10th | May 24th | Tuncay | Completed |
3.4 | Creation of Servlets for Task Dependency | 15 days | May 10th | May 24th | Mehmet | Completed |
3.5 | Creation of Quick Links | 5 days | May 10th | May 15th | Firat | Completed |
3.6 | Creation of User Manual | 8 days | May 25th | June 2nd | Tuncay & Firat | Completed |
3.7 | Creation of Installation Manual | 8 days | May 25th | June 2nd | Mehmet | Completed |
3.8 | Creation of Release Notes & Software Specification | 8 days | May 25th | June 2nd | Dogan | Completed |
3.9 | Integration | 3 days | June 1st | June 4th | Whole Team | Completed |
3.10 | Testing | 10 days | June 2nd | June 11th | Whole Team | Completed |
3.11 | Last Review | 7 days | June 11th | June 18th | Whole Team | Completed |
END OF PHASE 3 |