LIVING SCHEDULE
 Home

n
PROJECT IMPLEMENTATION START :   21 February 2005
EXPECTED END-TIME :   14 June 2005

 

RESPONSIBILITIES

START TIME

 DURATION

RESPONSIBLE STAFF

COMPLETED

PERCENTAGE

PDA Wireless Communication (802.11b) Design, Development and Testing

28 February

6 Weeks

Mustafa TURAN

100%

Web modules Implementation and Testing  

28 February

8 Weeks

Ahmet YIĞIT

100%

PDA Graphical User Interface Research Issues

7 March

2 Weeks

Mehmet YAZGEC, Mustafa TURAN

100%

PDA Graphical User Interface Implementation and Testing

21 March

5 Weeks

Mehmet YAZGEC

100%

Web Administration

21 February

 Whole Term

 Hakan SEVIMLI

100%

Database Administration

21 February

 Whole Term

 Hakan SEVIMLI

100%

Presentation

1 May

1 Week

Hakan SEVIMLI, Mustafa TURAN

100%

Web Modules Style Design  

7 March

6 Weeks

Hakan SEVIMLI

100%

Help Manual Construction

14 May

2 Weeks

Ahmet YIĞIT, Mehmet YAZGEC

100%

Integration of Wireless Modules

2 May

2 Weeks

Mustafa TURAN

100%

Testing Modules

14 May

2 Weeks

All of Us

100%

Testing Whole System

14 May

2 Weeks

All of Us

100%