LivingSchedule

Phase 1: CM Plan & Development Snapshot

 

Responsibilities

Start Date

Estimated Duration

Responsible Staff

Status

1.1

Creation of the Database & Login Module

Feb. 21st

3 days

Ömer Faruk & Ufuk

Completed

1.2

Creation of the Admin Module

Feb. 23rd

3 days

Ömer Faruk & Harun

Completed

1.3

Modification of the Instructor Module (File Transfer)

Feb. 27th

6 days

Ufuk & Harun

Completed

1.4

Modification of the Communication Module (Chat & Q/A Box & Control Box)

Mar. 3rd

6 days

Ömer Faruk & Ufuk & Harun

Completed

1.5

Creation of CM Plan

Mar 7th

3 days

Žahin & Ömer Faruk

Completed

1.6

Modification of the Whiteboard Module

Mar 9th

10 days

Harun

Completed

1.7

Creation of the Offline Tool

Mar. 7th

12 days

Ömer Faruk & Ufuk

Completed

1.8

Audio Streaming

Mar. 7th

13 days

Žahin

Completed

First Development Snapshot Demo

Phase 2: First Release and Test Specifications

 

Responsibilities

Start Date

Estimated Duration

Responsible Staff

Status

2.1

Modification of GUI’s

Mar. 21st

5 days

Harun & Ufuk

Completed

2.2

Audio Streaming

Mar. 22nd

14 days

Žahin & Ömer Faruk

Completed

2.3

Video Streaming

Mar. 25th

21 days

Harun & Ufuk

Completed

2.4

Whiteboard Module

Apr. 5th

10 days

Ömer Faruk & Harun

Completed

2.5

Offline Tool

Apr. 12th

7 days

Ufuk

Completed

2.6

Integration of the Video & Audio Streaming Modules to the system

Apr. 16th

10 days

Whole Team

Completed

2.7

Creation of Test Specifications

Apr. 20th

5 days

Whole Team

Completed

2.8

Error Detection

May. 2nd 

5 days

Whole Team

Completed

First Release

Phase 3: Final Product & Documentation

 

Responsibilities

Start Date

Estimated Duration

Responsible Staff

Status

3.1

Testing & Debugging

May. 10th 

10 days

Whole Team

Completed

3.2

User Manual Construction

May. 20th

5 days

Ömer Faruk & Ufuk

In Progress

3.3

Installation Manual Construction

May. 20th

5 days

Harun & Žahin

Not Started

3.4

Integration

May. 25th 

8 days

Whole Team

Not Started

3.5

Last Review

June 5th

10 days

Whole Team

Not Started

Old Schedule (25.03.2005-01.04.2005)