Living Schedule for CL@SS++
Date |
Task |
Progress | On Duty |
Feb 25-28 |
Time management & task sharing |
100% | All team |
|
|
|
|
Mar 1-6 |
Design review |
100% | All team |
|
|
|
|
Mar 6-7 |
Web page preparation |
100% | Ismail, Recep |
|
|
|
|
Mar 7-10 |
CM Plan |
100% | All team |
|
|
|
|
Mar 14 |
Snapshot Demo |
80% | All team |
|
|
|
|
Mar 10 |
Connection Module Start |
30% | Ismail, Yavuz |
|
|
|
|
Mar 10 |
Chat Module Start |
10% | Ismail, Hakan |
|
|
|
|
Mar 10 |
Video / Audio Handling Module Start |
10% | Hakan, Recep, Ismail |
|
|
|
|
Mar 10 |
Whiteboard Module Start |
10% | Recep, Ismail, Yavuz |
|
|
|
|
Mar 10 |
Application Sharing Module Start |
%15 | Yavuz |
Mar 10 |
Presentation Module Start |
%25 | Yavuz |
|
|
|
|
Apr 18 |
Testing Start |
0% | All Team |
|
|
|
|
Apr 25-28 |
System integration & deployment |
10% | All team |
|
|
|
|
Apr 28-May 6 |
Black box testing of whole system |
0% | Hakan, Recep |
|
|
|
|
Apr 28-May 4 |
GUI review & completion |
0% | Yavuz, Ismail |
|
|
|
|
May 4-6 |
Instructions for use and help documentation |
0% | Recep, Hakan |
|
|
|
|
May 6-11 |
Presentation preparation |
0% | Yavuz, Ismail |
|
|
|
|
May 12-16 |
First release critics investigation |
0% | All team |
|
|
|
|
May 17-28 |
Updates for final version |
0% | All team |
|
|
|
|
May 29-June 8 |
Final tests and error correction |
0% | All team |
|
|
|
|
June 8-11 |
Getting ready for final demonstration |
0% | All team |