Task Description |
Members in Charge |
Time Interval |
Situation |
Design Review |
All |
Feb 28 - Mar 07 |
Finished |
CM for Master Computer |
Ali - Burak |
Mar 07 - Mar 14 |
Finished |
CM for Microchip |
Tolga - Fatih |
Mar 07 - Mar 14 |
Finished |
Web Page Design Documnet Preparetion |
Ali - Burak - Tolga |
Mar 14 - Mar 21 |
Finished |
Web Page Design |
Fatih |
Mar 14 - Mar 21 |
Finished |
DB Design Review and Query Writing |
Ali - Burak |
Mar 21 - Mar 28 |
Finished |
Microchip Test |
Fatih - Tolga |
Mar 21 - Mar 28 |
Finished |
DB and Java-DB Connection Implementation |
Ali - Burak |
Mar 28 - Apr 11 |
Finished |
Implementing Microchip Code(Pooling) |
Fatih - Tolga |
Mar 28 - Apr 11 |
Finished |
DB Test |
Ali - Burak |
Apr 11 - Apr 18 |
Finished |
Microchip test with Reader |
Fatih - Tolga |
Apr 11 - Apr 18 |
Finished |
GUI Review and Master Computer Design |
All
|
Apr 18 - Apr 25 |
Finished |
Single Board Implementation |
All
|
Apr 25 - May 02 |
Finished |
First Release and Test Spec |
All
|
May 02 - May 09 |
Finished |
Test |
All
|
May 09 - May 23 |
Finished |
Network Security Implementation and test |
All
|
May 23 - May 30 |
Finished |
Correcting Bugs in Master Computer |
Ali - Burak
|
May 30 - Jan 06 |
Finished |
Correcting Bugs in Microchip and Single Computer |
Fatih - Tolga
|
May 30 - Jun 06 |
Finished |
Final Product Review and Release |
All
|
Jun 06 - Jun 13 |
Finished |