ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
1 | WP1:Documentation | 91 days | Thu 09.02.06 | Wed 10.05.06 | | 23% |
2 | Living Schedule | 2 days | Thu 09.02.06 | Fri 10.02.06 | All | 100% |
3 | Design Review | 2 days | Thu 16.02.06 | Fri 17.02.06 | All | 100% |
4 | Coding Standarts Review | 1 day | Tue 21.02.06 | Tue 21.02.06 | All | 100% |
5 | Configuration Management and Development Plan | 4 days | Tue 21.02.06 | Fri 24.02.06 | Sila, Ebru, Kevser, Bahar | 100% |
6 | User Manuals | 15 days | Sat 15.04.06 | Sat 29.04.06 | All | 0% |
7 | Installation Manual | 5 days | Sun 30.04.06 | Thu 04.05.06 | All | 0% |
8 | Release Notes and Software Specifications | 6 days | Fri 05.05.06 | Wed 10.05.06 | All | 0% |
9 | Test Specifications | 5 days | Sat 15.04.06 | Wed 19.04.06 | All | 0% |
10 | WP2:Detailed Web Page Preperation | 3 days | Tue 21.02.06 | Thu 23.02.06 | | 100% |
11 | Design of the New Page | 1 day | Tue 21.02.06 | Tue 21.02.06 | Cagla | 100% |
12 | Building of the Web Page | 1 day | Wed 22.02.06 | Wed 22.02.06 | Cagla | 100% |
13 | Transferring of Old Content to the New Page | 1 day | Thu 23.02.06 | Thu 23.02.06 | Cagla | 100% |
14 | WP3:Multimedia Production and GUI Preparation | 5 days | Sat 11.02.06 | Wed 15.02.06 | | 100% |
15 | Multimedia Production | 5 days | Sat 11.02.06 | Wed 15.02.06 | | 100% |
16 | Production of Models | 5 days | Sat 11.02.06 | Wed 15.02.06 | Sila, Cagla | 100% |
17 | Production of Audio | 3 days | Mon 13.02.06 | Wed 15.02.06 | Ebru | 100% |
18 | Graphical User Interface Production | 5 days | Sat 11.02.06 | Wed 15.02.06 | | 100% |
19 | Menubar | 1 day | Sat 11.02.06 | Sat 11.02.06 | Bahar | 100% |
20 | Toolbar | 2 days | Sun 12.02.06 | Mon 13.02.06 | Bahar | 100% |
21 | Toolbox | 5 days | Sat 11.02.06 | Wed 15.02.06 | Kevser | 100% |
22 | Integration With an OSG Window | 2 days | Tue 14.02.06 | Wed 15.02.06 | Ebru | 100% |
23 | WP4: Module Implementation | 57,6 days | Sat 11.02.06 | Sun 09.04.06 | | 16% |
24 | Fundamental Data Structures | 43,6 days | Sat 11.02.06 | Sun 26.03.06 | | 37% |
25 | Camera | 26 days | Wed 01.03.06 | Sun 26.03.06 | Bahar | 0% |
26 | Vehicle | 11 days | Sat 11.02.06 | Tue 28.02.06 | Sila | 60% |
27 | Wheel | 11 days | Sat 18.02.06 | Tue 28.02.06 | Sila | 80% |
28 | Frame | 26 days | Wed 01.03.06 | Sun 26.03.06 | Ebru | 0% |
29 | Object | 11 days | Sat 18.02.06 | Tue 28.02.06 | Bahar | 85% |
30 | Grid | 11 days | Sat 18.02.06 | Tue 28.02.06 | Sila | 10% |
31 | Road | 11 days | Sat 18.02.06 | Tue 28.02.06 | Ebru | 20% |
32 | Traffic Light | 11 days | Sat 18.02.06 | Tue 28.02.06 | Kevser | 60% |
33 | Traffic Sign | 11 days | Sat 18.02.06 | Tue 28.02.06 | Kevser | 100% |
34 | TrafficModel | 11 days | Sat 18.02.06 | Tue 28.02.06 | Cagla | 95% |
35 | Path | 11 days | Sat 18.02.06 | Tue 28.02.06 | Sila, Cagla | 10% |
36 | GUIEventHandler Module | 26 days | Wed 01.03.06 | Sun 26.03.06 | | 0% |
37 | Command Classes (undoable) | 26 days | Wed 01.03.06 | Sun 26.03.06 | Ebru | 0% |
38 | Command Classes (not undoable) | 26 days | Wed 01.03.06 | Sun 26.03.06 | Ebru | 0% |
39 | 0SGWindows Module | 37 days | Sat 18.02.06 | Sun 26.03.06 | | 9% |
40 | OSGWindows | 26 days | Wed 01.03.06 | Sun 26.03.06 | Kevser | 0% |
41 | Timeline | 11 days | Sat 18.02.06 | Tue 28.02.06 | Ebru | 50% |
42 | OSGEventHandler | 26 days | Wed 01.03.06 | Sun 26.03.06 | Kevser | 0% |
43 | Editor Checker Module | 14 days | Mon 27.03.06 | Sun 09.04.06 | Sila | 0% |
44 | AnimationWindow Module | 26 days | Wed 01.03.06 | Sun 26.03.06 | | 0% |
45 | AnimationWindow | 26 days | Wed 01.03.06 | Sun 26.03.06 | Sila, Cagla | 0% |
46 | AnimateEventHandler | 26 days | Wed 01.03.06 | Sun 26.03.06 | Sila, Cagla | 0% |
47 | PhysicsEngine Module | 26 days | Wed 01.03.06 | Sun 26.03.06 | Bahar | 0% |
48 | FileHandler Module | 14 days | Mon 27.03.06 | Sun 09.04.06 | Kevser | 0% |
49 | Audio Module | 14 days | Mon 27.03.06 | Sun 09.04.06 | Ebru | 0% |
50 | First Dev. Snapshot Demo | 0 mins | Sun 05.03.06 | Sun 05.03.06 | | 0% |
51 | WP5: Integration and Verification | 78 days | Tue 28.02.06 | Tue 16.05.06 | | 0% |
52 | Integration of Modules | 48 days | Tue 28.02.06 | Sun 16.04.06 | All | 0% |
53 | Verification | 44 days | Mon 03.04.06 | Tue 16.05.06 | | 0% |
54 | Test Case Design | 7 days | Mon 03.04.06 | Sun 09.04.06 | Bahar, Cagla | 0% |
55 | Test Case Implementation | 22 days | Sun 09.04.06 | Sun 30.04.06 | All | 0% |
56 | Run Modular Tests | 17 days | Sun 30.04.06 | Tue 16.05.06 | All | 0% |
57 | Run integration tests | 17 days | Sun 30.04.06 | Tue 16.05.06 | All | 0% |
58 | First release and Test Specification | 0 mins | Sun 23.04.06 | Sun 23.04.06 | | 0% |
59 | Presentations | 5 days | Sat 22.04.06 | Wed 26.04.06 | | 0% |
60 | Preparation of Presentation Outline | 5 days | Sat 22.04.06 | Wed 26.04.06 | All | 0% |
61 | Preparation of Presentation Slides | 5 days | Sat 22.04.06 | Wed 26.04.06 | All | 0% |
62 | Review | 8 days | Tue 16.05.06 | Tue 23.05.06 | All | 0% |
63 | Final Demo | 0 mins | Fri 26.05.06 | Fri 26.05.06 | | 0% |