IronCurtain

Company: WASD
Start: February 1, 2006
Finish: May 12, 2006
Report Date: March 19, 2006

Gantt Chart

WBS Name Work Week 6, 2006 Week 7, 2006 Week 8, 2006 Week 9, 2006 Week 10, 2006 Week 11, 2006 Week 12, 2006 Week 13, 2006 Week 14, 2006 Week 15, 2006 Week 16, 2006 Week 17, 2006 Week 18, 2006
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12
1 Setting up Database 12d 4h
1.1 Creating Tables 4d
F
1.2 Working out Table Interrelations 15d
M, K, F
1.3 Database Integration 14d
G, D
1.4 Revising Database 3d 4h
K
2 Plug-in Engine and Initial Plug-ins 18d
2.1 Base Plug-in Engine 16d
G, D
2.2 Modify Content Plug-in 20d
M, F
2.3 Modify Header Plug-in 20d
G, D
3 Initial Rules 30d
K, F
4 Secure Authentication 26d
M, K
5 Initial Web Management Console Design 26d
G, D
6 First Release
7 Testing First Release 20d
K, F
8 Logging And Reporting 15d
8.1 Logging and Reporting Engine 18d
K, G, D
8.2 Logging Interface to Plug-ins 15d
K, G, D
8.3 Statistics Generator 8d
M, F
9 HTTPS Support 20d
M, K, F
10 Plug-ins 15d
10.1 Image Plug-in 14d
M, F
10.2 Blocker Plug-in 14d
G, D
10.3 JavaScript Filter Plug-in 14d
G, F
10.4 Keyword Filter Plug-in 16d
G, D
10.5 Bandwidth Limiter Plug-in 16d
M, K
11 Rules 75d
M, K, G, F, D
12 Final Release
13 Testing Final Release 50d
M, K, G, F, D
14 Project Delivery

Tasks

WBS Name Start Finish Work Priority Complete Cost
1 Setting up Database Feb 1 Feb 17 12d 4h
1.1 Creating Tables Feb 1 Feb 6 4d 100%
1.2 Working out Table Interrelations Feb 7 Feb 13 15d 100%
1.3 Database Integration Feb 1 Feb 9 14d 100%
1.4 Revising Database Feb 14 Feb 17 3d 4h 50%
2 Plug-in Engine and Initial Plug-ins Feb 1 Feb 24 18d
2.1 Base Plug-in Engine Feb 1 Feb 10 16d 80%
2.2 Modify Content Plug-in Feb 13 Feb 24 20d 20%
2.3 Modify Header Plug-in Feb 13 Feb 24 20d 70%
3 Initial Rules Feb 27 Mar 17 30d 30%
4 Secure Authentication Feb 15 Mar 3 26d 20%
5 Initial Web Management Console Design Mar 1 Mar 17 26d 70%
6 First Release Mar 20 Mar 20
7 Testing First Release Mar 20 Mar 31 20d 0%
8 Logging And Reporting Feb 20 Mar 10 15d
8.1 Logging and Reporting Engine Feb 20 Feb 27 18d 50%
8.2 Logging Interface to Plug-ins Feb 28 Mar 6 15d 30%
8.3 Statistics Generator Mar 7 Mar 10 8d 10%
9 HTTPS Support Apr 3 Apr 11 20d 0%
10 Plug-ins Mar 13 Mar 31 15d
10.1 Image Plug-in Mar 13 Mar 21 14d 0%
10.2 Blocker Plug-in Mar 13 Mar 21 14d 0%
10.3 JavaScript Filter Plug-in Mar 13 Mar 21 14d 0%
10.4 Keyword Filter Plug-in Mar 22 Mar 31 16d 0%
10.5 Bandwidth Limiter Plug-in Mar 22 Mar 31 16d 0%
11 Rules Apr 10 Apr 28 75d 0%
12 Final Release May 1 May 1
13 Testing Final Release May 1 May 12 50d 0%
14 Project Delivery May 12 May 12

Resources

Name Short name Type Group Email Cost
Doğacan Güney D Work 0
Furkan Kuru F Work 0
Gökdeniz Karadağ G Work 0
Kaan Kahraman K Work 0
Mustafa Çoşkun M Work 0