LIVING SCHEDULE
TASK NAME | DURATION | START DATE | END DATE | ASSIGNED | DONE |
WP0. Project Management | |||||
Living Schedule | 3 days | 23.02.2007 | 25.02.2007 | All | 100% |
Project web page | 14 days | 26.02.2007 | 11.03.2007 | Fırat | 100% |
Configuration management plan | 8 days | 04.03.2007 | 11.03.2007 | all | 100% |
WP1. Prototype and Design Review | |||||
Mailing list requirements review | 9 days | 25.02.2007 | 05.03.2007 | Yunus | 100% |
Security module re-design | 19 days | 25.02.2007 | 15.03.2007 | Yusuf,Dilek | 100% |
Ensuring performance | 9 days | 25.02.2007 | 05.03.2007 | Fırat | 100% |
Forum GUI enhancement | 24 days | 25.02.2007 | 20.03.2007 | Eda | 80% |
WP2. SMTP2NNTP Module Development | |||||
SMTP2NNTP article format conversion | 13 days | 06.03.2007 | 18.03.2007 | Yusuf | 100% |
Spam filtering feature | 15 days | 20.03.2007 | 03.04.2007 | Yusuf,Eda | 100% |
Virus Filtering Feature | 7 days | 21.03.2007 | 28.03.2007 | Dilek | 100% |
Unit testing | 3 days | 04.04.2007 | 07.04.2007 | Yusuf,Eda | 100% |
SMTP2NNTP and NNTP2SMTP integration | 3 days | 08.04.2007 | 10.04.2007 | Yusuf,Eda | 100% |
Performance testing | 3 days | 10.04.2007 | 12.04.2007 | Yusuf | 100% |
Security testing | 3 days | 13.04.2007 | 15.04.2007 | Yusuf,Eda | 100% |
Globalization testing | 2 days | 16.04.2007 | 17.04.2007 | Eda | 0% |
First release | 0 day | 18.04.2007 | 18.04.2007 | Yusuf,Eda | 100% |
Beta testing | 5 days | 19.04.2007 | 23.04.2007 | Yusuf,Eda | 100% |
Improvements | 12 days | 19.04.2007 | 30.04.2007 | Yusuf,Eda | 100% |
Final release | 0 day | 01.05.2007 | 01.05.2007 | Yusuf,Eda | 100% |
WP3. User Authentication Module Implementation | |||||
Login module implementation | 15 days | 07.03.2007 | 21.03.2007 | Fırat | 100% |
SSL certification implementation | 25 days | 07.03.2007 | 31.03.2007 | Yunus | 60% |
User delegation implementation | 26 days | 22.03.2007 | 16.04.2007 | Fırat | 100% |
Database security configuration | 16 days | 01.04.2007 | 16.04.2007 | Yunus | 100% |
Alpha testing | 6 days | 17.04.2007 | 22.04.2007 | Yunus,Fırat | 80% |
First Release | 0 day | 23.04.2007 | 23.04.2007 | Yunus,Fırat | 100% |
Beta testing and debugging | 8 days | 24.04.2007 | 01.05.2007 | Yunus,Fırat | 80% |
Improvements | 8 days | 24.04.2007 | 01.05.2007 | Yunus,Fırat | 100% |
Final release | 0 day | 01.05.2007 | 01.05.2007 | Yunus,Fırat | 100% |
WP4. Admin Module Implementation | |||||
Admin GUI implementation | 2 days | 06.03.2007 | 15.03.2007 | Dilek | 80% |
Server configuration implementation | 2 days | 16.03.2007 | 23.03.2007 | Dilek, Yunus | 70% |
Newsgroup and mailing list conf. İmplementation | 8 days | 24.03.2007 | 01.04.2007 | Dilek | 20% |
User management implementation | 6 days | 10.04.2007 | 15.04.2007 | Dilek | 90% |
Logging implementation | 5 days | 16.04.2007 | 20.04.2007 | Dilek, Fırat | 70% |
Alpha testing | 2 days | 21.04.2007 | 24.04.2007 | Dilek | 70% |
First Release | 0 day | 25.04.2007 | 25.04.2007 | Dilek | 70% |
Beta testing and debugging | 3 days | 26.04.2007 | 30.04.2007 | Dilek | 70% |
Improvements | 3 days | 26.04.2007 | 30.04.2007 | Dilek | 70% |
Final release | 0 day | 01.05.2007 | 01.05.2007 | Dilek | 70% |
WP5: Finalizing Package | |||||
Integrating Modules | 2 days | 02.05.2007 | 03.05.2007 | All | 70% |
First Release Alpha Testing | 2 days | 04.05.2007 | 05.05.2007 | All | 70% |
First Release Beta Testing & Debugging | 2 days | 04.05.2007 | 05.05.2007 | All | 70% |
First Release | 0 day | 06.05.2007 | 06.05.2007 | All | 70% |
Improvements | 30 days | 08.05.2007 | 08.06.2007 | All | 70% |
Final Release Alpha Testing | 4 days | 09.06.2007 | 12.06.2007 | All | 70% |
Final Release Beta Testing & Debugging | 4 days | 13.06.2007 | 16.06.2007 | All | 70% |
Final Release | 0 day | 17.06.2007 | 17.06.2007 | All | 70% |