The Living Schedule of Resolvesoft

Task Duration Start Date Finish Date Assigned To Status
Configuration Management Planning 6 days 25 February 2 March All Members %100 Completed
Web Page Preparation 5 days 24 February 28 February Ulas %100 Completed
Other Group's Design Review 7 days 26 February 5 March All Members %100 Completed
Design & Demo Review 6 days 19 February 24 February All Members %100 Completed
Preparation for Team Presentation 7 days 30 April 6 May All Members %100 Completed
Coding 84 days 19 February 13 May All Members %0 Completed
Simulation Module 40 days 19 February 30 March All Members %95 Completed
Simulator Class 40 days 19 February 30 March Fatih, Adem %90 Completed
SimulatorGUI Class 10 days 24 February 5 March Adem, Fatih %95 Completed
StimuliPipe Class 3 days 17 March 19 March Fatih %20 Completed
Breakpoint Class 4 days 19 March 22 March Adem %20 Completed
PICMemory Class 2 days 28 February 1 March Fatih %20 Completed
SimulationConfiguration Class 10 days 12 March 21 March Adem %20 Completed
StimuliRecorder Class 7 days 2 March 8 March Hayri %20 Completed
StimuliFile Class 2 days 2 March 3 March Ulas %20 Completed
StimuliGenerator Class 7 days 2 March 8 March Ulas %20 Completed
Compilation Module 15 days 20 March 3 April Hayri, Fatih %0 Completed
CompilerWrapper Class 3 days 3 April 10 April Hayri %0 Completed
Assembler 20 days 25 February 16 March Adem %100 Completed
Disassembler 10 days 22 February 3 March Ulas %50 Completed
Finalization of Subset of the C Language 2 days 20 February 21 February All Members %0 Completed
Object File Generator 4 days 4 April 7 April Fatih %0 Completed
Object File Support for Simulator 4 days 8 April 11 April Fatih %0 Completed
Representing Compilation Output on the GUI 2 days 13 April 14 April Hayri %50 Completed
Project/File Module 10 days 17 April 26 April Hayri %0 Completed
Project Manager GUI 3 days 24 April 26 April Fatih %0 Completed
Implementation Menu Items and Callbacks of Notepad++ 5 days 22 April 26 April Fatih %0 Completed
FileManager Class 4 days 14 April 17 April Hayri %0 Completed
Project Class 7 days 17 April 23 April Adem %100 Completed
Loader Module 20 days 1 April 20 April Ulas, Fatih, Adem %0 Completed
HexFileCoDec Class 5 days 10 April 14April Fatih %100 Completed
Loader Class 20 days 1 April 20 April Ulas %0 Completed
Loader GUI 5 days 16 April 20 April Adem %0 Completed
First Integration 2 days 10 March 11 March All Members %0 Completed
Controler Class 2 days 10 March 11 March Hayri %0 Completed
Second Integration 3 days 27 April 29 April All Members %0 Completed
Integration of Notepad++ 3 days 27 April 29 April Fatih %0 Completed
Third Integration 5 days 6 June 10 June All Members %0 Completed
Breakpoint Input From GUI 3 days 6 June 8 June Adem %0 Completed
Testing 23 days 14 May 5 June All Members %0 Completed
Simulator Unit Testing 2 days 14 May 15 May Fatih %50 Completed
Compiler Unit Testing 2 days 14 May 15 May Hayri %0 Completed
Project/File Unit Testing 2 days 14 May 15 May Adem %60 Completed
Loader Unit Testing 2 days 14 May 15 May Ulas %0 Completed
Blackbox Testing for First Release 2 days 9 March 10 March All Members %0 Completed
Blackbox Testing for Final Release 2 days 9 May 10 May All Member %0 Completed
Integration Testing 11 days 3 May 13 May All Member %30 Completed
System Validation 9 days 14 May 22 May All Member %0 Completed
Documentation 18 days 23 May 10 June All Members %0 Completed
Completion of the Internal Documentation 9 days 23 May 1 June All Members %0 Completed
Preparation of User Manuals 9 days 2 June 10 June Ulas %0 Completed
Preparation of Developer Manuals 9 days 2 June 10 June Fatih, Hayri, Adem %0 Completed
Final Release   11 June 11 June All Members %0 Completed