LIVING SCHEDULE
Task ID | Task | Responsible | Percentage Completed |
WEEK I (18.02.2008 - 24.02.2008) |
|||
1
|
Preparation of Living Schedule | AIVA Team | %100 |
2 | Web Site Revision | Damir , Emrah | %100 |
WEEK II (25.02.2008 - 02.03.2008) |
|||
3 | Design Review | AIVA Team | %100 |
4 | Research on CVS | Fatma, Damir | %60 |
5 | Research on Alternative Tools | Derya | %50 |
WEEK III (03.03.2008 - 09.03.2008) |
|||
6 | Research on CVS | Fatma , Damir | %90 |
7 | CVS Setup | AIVA Team | %60 |
8 | Preparation of Configuration Management Plan | AIVA Team | %100 |
9 | Web Site Completion and Launch | Damir , Emrah | %100 |
10 | Demo Review | AIVA Team | %100 |
WEEK IV (10.03.2008 - 16.03.2008) |
|||
11 | Job-seeker Module Development | Damir , Emrah | %30 |
12 | Project Database Preparation for users and job-seeker module | Derya | %70 |
13 | User Interface Preparation for Job-seeker module | Fatma | %40 |
14 | Snapshot Demo Preparation | AIVA Team | %90 |
WEEK V (17.03.2008 - 23.03.2008) |
|||
15 | Job-seeker Module Development | Damir, Emrah | %60 |
16 | Project Database Preparation for job-seeker module | Fatma, Derya | %100 |
17 | Login and Registration Module Development | AIVA Team | %100 |
WEEK VI (24.03.2008 - 30.03.2008) |
|||
18 | Finalizing Job-seeker Module Development | Damir, Emrah | %90 |
19 | Finalizing Main Page development | AIVA Team | %80 |
20 | Employer Module Development - Part 1 | AIVA Team | %10 |
21 | Getting used to with Integration Server | Fatma, Derya | %50 |
WEEK VII (31.03.2008 - 06.04.2008) |
|||
22 | Employer Module Development | AIVA Team | %20 |
23 | Project Database Preparation for employer module | AIVA Team | %30 |
23 | Completion of Version 1 | AIVA Team | %100 |
WEEK VIII (07.04.2008 - 13.04.2008) |
|||
24 | Beginning to use different tools(Eclipse with plug-in) | AIVA Team | %100 |
25 | External web portal job-seeker module | Fatma, Damir | %50 |
26 | Authentication module development | Emrah, Derya | %100 |
WEEK IX (14.04.2008 - 20.04.2008) |
|||
27 | Job-seeker module development | Emrah, Derya | %30 |
28 | External web portal job-seeker module | Fatma, Damir | %80 |
29 | Changes made on our system database | AIVA Team | %100 |
WEEK X (21.04.2008 - 27.04.2008) |
|||
30 | Job-seeker module development | Emrah, Derya | %80 |
31 | Web service integration for job-seeker module | AIVA Team | %60 |
32 | External web portal job-seeker module | Fatma, Damir | %100 |
33 | Completion of Version 1 | AIVA Team | %100 |
WEEK XI (28.04.2008 - 04.05.2008) |
|||
34 | External web-portal employer module development | Fatma | %50 |
35 | Employer module development | Derya, Damir | %20 |
35 | Creation of the database tables for employer module | Emrah | %100 |
WEEK XII (05.05.2008 - 11.05.2008) |
|||
37 | Web service integration for registration module | Damir | %80 |
37 | Employer module development | AIVA Team | %40 |
37 | Web service integration for job-seeker module | AIVA Team | %100 |
38 | Preparation of Team Presentations | AIVA Team | %100 |
WEEK XIII (12.05.2008 - 18.05.2008) |
|||
39 | Team Presentation | Fatma, Damir | %100 |
40 | Job Seeker Notification Module Development | AIVA Team | %20 |
WEEK XIV (19.05.2008 - 25.05.2008) |
|||
41 | External web-portal employer module development | Fatma, Damir | %100 |
42 | Employer module development | Emrah, Derya | %70 | 42 | Job Seeker Notification Module Development | AIVA Team | %50 |
WEEK XV (26.05.2008 - 01.06.2008) |
|||
43 | Web service integration for employer module | AIVA Team | %100 |
44 | Employer module development | AIVA Team | %100 |
44 | Administrator module development | AIVA Team | %40 |
WEEK XVI (02.06.2008 - 08.06.2008) |
|||
45 | Administator Module Development | AIVA Team | %100 |
46 | Operator Module Development | AIVA Team | %20 |
47 | User Interface Preparation for Administator and Operator modules | AIVA Team | %100 |
WEEK XVII (09.06.2008 - 15.06.2008) |
|||
48 | System Testing | AIVA Team | %100 |
49 | Integration Testing | AIVA Team | %100 |
50 | Final Demo Preparation | AIVA Team | %100 |
51 | Final Package Completion | AIVA Team | %100 |