Completed Tasks
- Database Design and Creation
Details : The design phase of the databases are completed. The related tables are created using PostGreSQL. The main structure is constructed and there will not be any major changes after this point. - Java Classes for Database Operations
Implementation
Details : All the functions for database operations are implemented in Java. Small changes may be done depending on the needs. - User Interface Implementation
Details : Research for materials to be used on web site is done. Implementation started. Parts will be modified as new codes in other parts are developed so it is an on-going process. Development has been improved by partitioning the user interface into components. All JSP files are written. Integration of JSP's are completed. Now web services integration are being made. - Web Services development
Details : We have finished writing web services for both portal and JSWS's. Only unmatched job declaration service is missing because it is complicated. But we will complete it in a short time. - Integration and Testing
Details : Integration of the components are finished. Most of the testing of the general system behaviour is completed.
- Documentation
Details : We have written the documentation files required for our project. We published them under Project Files section with the complete distribution of our project.
Previous Schedules
- 22.02.2008 - Living Schedule 1
- 02.03.2008 - Living Schedule 2
- 12.03.2008 - Living Schedule 3
- 26.03.2008 - Living Schedule 4
- 26.03.2008 - Living Schedule 5
- 02.04.2008 - Living Schedule 6
- 09.04.2008 - Living Schedule 7
- 16.04.2008 - Living Schedule 8
- 23.04.2008 - Living Schedule 9
- 30.04.2008 - Living Schedule 10
- 07.05.2008 - Living Schedule 11
- 14.05.2008 - Living Schedule 12
- 21.05.2008 - Living Schedule 13
- 28.05.2008 - Living Schedule 14
- 04.06.2008 - Living Schedule 15