Apr 22 2009

Summary of The Last Week

Eray

It was really a busy week for the project. I have completed the Venue Selection, Add Venue and Update Status parts with the help of Gokhan. I also helped our team for integration tasks. I added some new features to Google Maps component and also helped Cansin to improve capabilities of it. I also worked on AddEvent part and its client side has totally been completed. I am going to complete server side of it when some conflicts be solved.


Apr 15 2009

Summary of This Week

Eray

The work done can be listed as follow:

  • Google Map component’s ajax implementation has been replaced with jquery’s ajax handling functions.
  • Google Map component has been embedded into VenueSelection page.
  • VenueSelection page’s parameter passing mechanism implemented.
  • Validators for AddVenue page has been written.
  • AddVenue and UpdateStatus is under construct. I have to work with Gokhan to solve some conflicts.