Project Start Date: Tue 28.09.04
Project Finish Date: Tue 14.06.05
(Last updated at 12.06.2005) FINAL RELEASE
| ID | Name
|
Duration | Start_Date | Finish | Assigned To | Percent Work Complete |
|---|---|---|---|---|---|---|
| 1 | Planning
|
12 days | Tue 28.09.04 | Wed 13.10.04 | 100% | |
| 2 | Project Proposal
|
11 days | Tue 28.09.04 | Tue 12.10.04 | 100% | |
| 3 | Milestone
|
0 days | Wed 13.10.04 | Wed 13.10.04 | 100% | |
| 4 | RequirementsAnalysis
|
32 days | Thu 14.10.04 | Wed 24.11.04 | 100% | |
| 5 | Specification Research
|
5 days | Thu 14.10.04 | Tue 19.10.04 | 100% | |
| 6 | Web Questionnaire
|
29 days | Thu 14.10.04 | Fri 19.11.04 | 100% | |
| 7 | Requirements Specification
|
18 days | Mon 01.11.04 | Tue 23.11.04 | 100% | |
| 8 | Milestone
|
0 days | Wed 24.11.04 | Wed 24.11.04 | 100% | |
| 9 | Initial Design
|
10 days | Thu 25.11.04 | Wed 08.12.04 | 100% | |
| 10 | Design Drafts for Modules
|
4 days | Thu 25.11.04 | Tue 30.11.04 | 100% | |
| 11 | Initial Design Specification
|
7 days | Mon 29.11.04 | Tue 07.12.04 | 100% | |
| 12 | Milestone
|
0 days | Wed 08.12.04 | Wed 08.12.04 | 100% | |
| 13 | Detailed Design
|
24 days | Thu 09.12.04 | Mon 10.01.05 | 100% | |
| 14 | Draft Design Specification
|
6 days | Thu 09.12.04 | Thu 16.12.04 | 100% | |
| 15 | Object Oriented Architectural &
Procedural Design
|
13 days | Fri 10.12.04 | Mon 27.12.04 | 100% | |
| 16 | Complete Class Diagrams
|
10 days | Wed 22.12.04 | Mon 03.01.05 | 100% | |
| 17 | Hardware Design
|
22 days | Fri 10.12.04 | Fri 07.01.05 | 100% | |
| 18 | Interface Design
|
5 days | Fri 31.12.04 | Thu 06.01.05 | 100% | |
| 19 | Test Provisions
|
19 days | Thu 16.12.04 | Mon 10.01.05 | 100% | |
| 20 | Design Specification
|
6 days | Mon 03.01.05 | Mon 10.01.05 | 100% | |
| 21 | Milestone
|
0 days | Mon 10.01.05 | Mon 10.01.05 | 100% | |
| 22 | Pre - Implementation
|
23 days | Mon 20.12.04 | Wed 19.01.05 | 100% | |
| 23 | Prototype
|
23 days | Mon 20.12.04 | Tue 18.01.05 | 100% | |
| 24 | Milestone
|
0 days | Wed 19.01.05 | Wed 19.01.05 | 100% | |
| 25 | Implementation
|
100 days? | Tue 01.02.05 | Tue 14.06.05 | 100% | |
| 26 | Prototype review
|
5 days | Tue 01.02.05 | Mon 07.02.05 | 100% | |
| 27 | Implementation Initials
|
8 days | Tue 01.02.05 | Thu 10.02.05 | 100% | |
| 28 | System Database Modules
|
4 days? | Sun 13.03.05 | Wed 16.03.05 | 100% | |
| 29 | DB Tables
|
4 days | Sun 13.03.05 | Wed 16.03.05 | Bilal;Okan;Kerim | 100% |
| 30 | DB Queries
|
4 days? | Sun 13.03.05 | Wed 16.03.05 | Bilal;Okan;Kerim | 100% |
| 31 | Module
|
79 days? | Tue 08.02.05 | Thu 26.05.05 | 52% | |
| 32 | Wireless Communication Modules
|
60 days? | Tue 08.02.05 | Thu 28.04.05 | Özkan;Kerim | 10% |
| 33 | Wireless Communication Modules
|
4 days | Tue 03.05.05 | Fri 06.05.05 | Bilal;Okan | 100% |
| 34 | Card Implementation
|
66 days | Mon 14.02.05 | Thu 12.05.05 | 100% | |
| 35 | Modifying PIC program, circuit
design,etc.
|
52 days | Mon 14.02.05 | Fri 22.04.05 | 100% | |
| 36 | Modifying PIC program for the first
development snapshot
|
6 days | Fri 11.03.05 | Thu 17.03.05 | Okan;Bilal | 100% |
| 37 | Modifying PIC program & circuit
design for Regular Demo (I)
|
10 days | Fri 18.03.05 | Thu 31.03.05 | Okan;Bilal | 100% |
| 38 | Modifying PIC program & circuit
design for Regular Demo (II)
|
10 days | Fri 01.04.05 | Thu 14.04.05 | Okan;Bilal | 100% |
| 39 | Modifying PIC program & circuit
design for Regular Demo (III)
|
11 days | Fri 15.04.05 | Thu 28.04.05 | Okan;Bilal | 100% |
| 40 | Modifying PIC program & circuit
design for Regular Demo (IV)
|
10 days | Fri 29.04.05 | Thu 12.05.05 | Okan;Bilal | 100% |
| 41 | Main-Board Program
|
61 days? | Tue 15.02.05 | Fri 06.05.05 | 30% | |
| 42 | Modifying mainboard program
|
48 days? | Tue 15.02.05 | Tue 19.04.05 | 0% | |
| 43 | Interface mainboard program with MySQL
for the first development snapshot
|
6 days | Fri 11.03.05 | Thu 17.03.05 | Özkan;Kerim | 100% |
| 44 | Integration mainboard program with MySQL
for Regular Demo (III)
|
31 days | Fri 18.03.05 | Thu 28.04.05 | Özkan;Kerim | 10% |
| 45 | Interface to the C4 Control Card for the
first development snapshot
|
6 days | Fri 11.03.05 | Thu 17.03.05 | Okan;Bilal | 100% |
| 46 | Correction of the interface(from first
development snapshot) to the C4 Control Card for Regular Demo(I)
|
10 days | Fri 18.03.05 | Thu 31.03.05 | Okan | 100% |
| 47 | Modifying OS (Linux that bootable from
flash disk) for using MySQL and Wireless for Regular Demo (III)
|
31 days | Fri 18.03.05 | Thu 28.04.05 | Özkan;Kerim | 3% |
| 48 | Modifying OS (Linux that bootable from
flash disk) and Wireless for First Release
|
4 days | Tue 03.05.05 | Fri 06.05.05 | Okan;Bilal | 100% |
| 49 | GUI Implementation
|
43 days | Mon 07.03.05 | Mon 02.05.05 | 100% | |
| 50 | Implementing User Interfaces with PHP
and MySQL
|
31 days | Mon 07.03.05 | Fri 15.04.05 | 100% | |
| 51 | Designing and Implementing first level
of main menu of the GUIs for Regular Demo (I)
|
10 days | Fri 18.03.05 | Thu 31.03.05 | Bilal | 100% |
| 52 | Designing and Implementing the GUIs for
Regular Demo (II)
|
10 days | Fri 01.04.05 | Thu 14.04.05 | Bilal | 100% |
| 53 | Designing and Implementing the GUIs for
Regular Demo (III)
|
11 days | Fri 15.04.05 | Thu 28.04.05 | Bilal;Okan | 100% |
| 54 | Designing and Implementing the GUIs for
First Release
|
6 days | Mon 25.04.05 | Mon 02.05.05 | Bilal;Okan | 100% |
| 55 | Administrator Program
|
47 days | Mon 07.03.05 | Fri 06.05.05 | 100% | |
| 56 | Integration of admin program database
with main board program by means of network
|
32 days | Mon 07.03.05 | Sat 16.04.05 | 100% | |
| 57 | Implementing main base of admin program
(network communication with main boards) for Regular Demo (II)
|
20 days | Fri 18.03.05 | Thu 14.04.05 | Okan;Kerim | 100% |
| 58 | Implementing admin program (network
communication with main boards) for Regular Demo (III)
|
11 days | Fri 15.04.05 | Thu 28.04.05 | Okan;Bilal | 100% |
| 59 | Implementing admin program (network
communication with main boards) for First Release
|
10 days | Mon 25.04.05 | Fri 06.05.05 | Okan;Bilal | 100% |
| 60 | First development shapshot-Milestone
|
0 days | Thu 17.03.05 | Thu 17.03.05 | 100% | |
| 61 | Regular Demo (I)
|
0 days | Thu 31.03.05 | Thu 31.03.05 | 100% | |
| 62 | Regular Demo (II)
|
0 days | Thu 14.04.05 | Thu 14.04.05 | 100% | |
| 63 | Regular Demo (III)
|
0 days | Thu 28.04.05 | Thu 28.04.05 | 100% | |
| 64 | Regular Demo (IV)
|
0 days | Thu 12.05.05 | Thu 12.05.05 | 100% | |
| 65 | Regular Demo (V)
|
0 days | Thu 26.05.05 | Thu 26.05.05 | 100% | |
| 66 | Performance Improvement
|
15 days | Mon 25.04.05 | Fri 13.05.05 | Okan;Bilal | 100% |
| 67 | Tests
|
28 days | Mon 02.05.05 | Tue 07.06.05 | Okan;Bilal | 100% |
| 68 | First version Release - Milestone
|
0 days | Mon 02.05.05 | Mon 02.05.05 | Okan;Bilal | 100% |
| 69 | Implementation (final)
|
10 days | Tue 31.05.05 | Sun 12.06.05 | Okan;Bilal | 100% |
| 70 | Final Demo of the project
|
2 days | Mon 13.06.05 | Tue 14.06.05 | 90% | |
| 71 | Documentation
|
97 days | Wed 02.02.05 | Sun 12.06.05 | 100% | |
| 72 | Web Page of the project
|
94 days | Wed 02.02.05 | Wed 08.06.05 | Bilal | 100% |
| 73 | Living Schedule
|
78 days | Mon 21.02.05 | Fri 03.06.05 | Okan | 100% |
| 74 | Peer Evaluation - Design
Review
|
4 days | Tue 01.03.05 | Fri 04.03.05 | Whole Team | 100% |
| 75 | Configuration Management Plan
|
5 days | Tue 08.03.05 | Sun 13.03.05 | Whole Team | 100% |
| 76 | Test Documentation
|
6 days | Fri 29.04.05 | Fri 06.05.05 | Kerim;Özkan | 100% |
| 77 | Compilation manual
|
10 days | Mon 30.05.05 | Fri 10.06.05 | Okan;Bilal | 100% |
| 78 | User and administration manual
|
10 days | Fri 27.05.05 | Fri 10.06.05 | Kerim;Özkan | 100% |
| 79 | Developers guide
|
10 days | Mon 30.05.05 | Fri 10.06.05 | Okan;Bilal | 100% |
| 80 | Installation manual
|
10 days | Mon 30.05.05 | Sun 12.06.05 | Okan;Bilal | 100% |
| 81 | Milestone
|
0 days | Wed 08.06.05 | Wed 08.06.05 | 100% | |
| 82 | Customer Evaluation
|
2 days? | Sun 12.06.05 | Mon 13.06.05 | 0% | |
| 83 | Feedback
|
2 days? | Sun 12.06.05 | Mon 13.06.05 | 0% | |
| 84 | Milestone
|
0 days | Mon 13.06.05 | Mon 13.06.05 | 0% |