LIVING SCHEDULE |
PROJECT IMPLEMENTATION START : |
10 December 2004 |
EXPECTED END-TIME : |
15 June 2005 |
RESPONSIBILITIES |
START TIME |
DURATION |
RESPONSIBLE STAFF |
WEB Module Food Service |
17-Feb |
1 Week |
Mustafa |
WEB Module User Management |
February |
1 Week |
Mustafa |
23 |
|||
WEB Module Table Reservation |
1-Mar |
1 Week |
Rovsen |
WEB Module Upgrade |
7-Mar |
3 Weeks |
Mustafa-Rovsen-Evren |
Cash-Desk Module Super User Part |
February |
3 Weeks |
Rovsen |
10 |
|||
Cash-Desk Module Normal User Part |
11-Mar |
2 Weeks |
All Staff |
Learning Something About Wireless Technologies |
24-Mar |
2 Days |
All Staff |
Cash-Desk Module-Stock Management Part |
26-Mar |
1 Week |
Rovsen-Guner |
Kitchen Module |
10-Apr |
1 Week |
Mustafa-Evren |
Integrating Cash-Desk,Kitchen and Web Modules |
17-Apr |
1 Week |
All Staff |
For Testing Purposes |
|||
Learning Wireless Techology Properly and Writing Test Codes On PDA |
24-Apr |
2 Weeks |
All Staff |
Waiter-PDA Module |
7-May |
2 Weeks |
Mustafa-Evren |
User Management Part |
|||
Waiter –PDA Module |
7-May |
2 Weeks |
Rovsen-Guner |
Ordering Part |
|||
Integrating Modules |
21-May |
1 Week |
All Staff |
Testing of Modules |
28-May |
1 Week |
All Staff |
Testing of Whole System |
4-Jun |
4 Days |
All Staff |
Preparing Help Manual |
8-Jun |
1 Week |
All Staff |
|
Completed |
|
On-Progress |
|
Not Started Yet |