LIVING SCHEDULE

 

 

PROJECT IMPLEMENTATION START :  

10 December 2004

EXPECTED END-TIME :  

15 June 2005

 

RESPONSIBILITIES

START TIME

DURATION

RESPONSIBLE STAFF

 WEB Module Food Service

17-Feb

1 Week

Mustafa

WEB Module User Management

  February

1 Week

Mustafa

23

WEB Module Table Reservation

1-Mar

1 Week

Rovsen

WEB Module Upgrade

7-Mar

3 Weeks

Mustafa-Rovsen-Evren

Cash-Desk Module Super User Part

February

3 Weeks

Rovsen

10

Cash-Desk Module Normal User Part

11-Mar

2 Weeks

All Staff

Learning Something About Wireless Technologies

24-Mar

2 Days

All Staff

Cash-Desk Module-Stock Management Part

26-Mar

1 Week

Rovsen-Guner

Kitchen Module

10-Apr

1 Week

Mustafa-Evren

Integrating Cash-Desk,Kitchen and Web Modules

17-Apr

1 Week

All Staff

For Testing Purposes

Learning Wireless Techology Properly and Writing Test Codes On PDA

24-Apr

2 Weeks

All Staff

Waiter-PDA Module

7-May

2 Weeks

Mustafa-Evren

User Management Part

Waiter –PDA Module

7-May

2 Weeks

Rovsen-Guner

Ordering Part

Integrating Modules

21-May

1 Week

All Staff

Testing of Modules

28-May

1 Week

All Staff

Testing of Whole System

4-Jun

4 Days

All Staff

Preparing Help Manual

8-Jun

1 Week

All Staff

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 




 

  Completed

 

  On-Progress

 

  Not Started Yet