| ID |
Task Name
|
Duration |
Start |
Finish |
Resource
Names |
% Complete |
| 1 |
WP1:Documentation
|
91 days |
Thu 09.02.06 |
Wed 10.05.06 |
|
23% |
| 2 |
Living
Schedule
|
2 days |
Thu 09.02.06 |
Fri 10.02.06 |
All |
100% |
| 3 |
Design Review
|
2 days |
Thu 16.02.06 |
Fri 17.02.06 |
All |
100% |
| 4 |
Coding
Standarts Review
|
1 day |
Tue 21.02.06 |
Tue 21.02.06 |
All |
100% |
| 5 |
Configuration
Management and Development Plan
|
4 days |
Tue 21.02.06 |
Fri 24.02.06 |
Sila, Ebru, Kevser, Bahar |
100% |
| 6 |
User Manuals
|
15 days |
Sat 15.04.06 |
Sat 29.04.06 |
All |
0% |
| 7 |
Installation
Manual
|
5 days |
Sun 30.04.06 |
Thu 04.05.06 |
All |
0% |
| 8 |
Release Notes
and Software Specifications
|
6 days |
Fri 05.05.06 |
Wed 10.05.06 |
All |
0% |
| 9 |
Test
Specifications
|
5 days |
Sat 15.04.06 |
Wed 19.04.06 |
All |
0% |
| 10 |
WP2:Detailed
Web Page Preperation
|
3 days |
Tue 21.02.06 |
Thu 23.02.06 |
|
100% |
| 11 |
Design of the
New Page
|
1 day |
Tue 21.02.06 |
Tue 21.02.06 |
Cagla |
100% |
| 12 |
Building of
the Web Page
|
1 day |
Wed 22.02.06 |
Wed 22.02.06 |
Cagla |
100% |
| 13 |
Transferring
of Old Content to the New Page
|
1 day |
Thu 23.02.06 |
Thu 23.02.06 |
Cagla |
100% |
| 14 |
WP3:Multimedia
Production and GUI Preparation
|
5 days |
Sat 11.02.06 |
Wed 15.02.06 |
|
100% |
| 15 |
Multimedia
Production
|
5 days |
Sat 11.02.06 |
Wed 15.02.06 |
|
100% |
| 16 |
Production of
Models
|
5 days |
Sat 11.02.06 |
Wed 15.02.06 |
Sila, Cagla |
100% |
| 17 |
Production of
Audio
|
3 days |
Mon 13.02.06 |
Wed 15.02.06 |
Ebru |
100% |
| 18 |
Graphical
User Interface Production
|
5 days |
Sat 11.02.06 |
Wed 15.02.06 |
|
100% |
| 19 |
Menubar
|
1 day |
Sat 11.02.06 |
Sat 11.02.06 |
Bahar |
100% |
| 20 |
Toolbar
|
2 days |
Sun 12.02.06 |
Mon 13.02.06 |
Bahar |
100% |
| 21 |
Toolbox
|
5 days |
Sat 11.02.06 |
Wed 15.02.06 |
Kevser |
100% |
| 22 |
Integration
With an OSG Window
|
2 days |
Tue 14.02.06 |
Wed 15.02.06 |
Ebru |
100% |
| 23 |
WP4:
Module Implementation
|
85,3 days |
Sat 11.02.06 |
Sun 07.05.06 |
|
68% |
| 24 |
Fundamental
Data Structures
|
44 days |
Sat 11.02.06 |
Sun 26.03.06 |
|
93% |
| 25 |
Camera
|
26 days |
Wed 01.03.06 |
Sun 26.03.06 |
Bahar |
85% |
| 26 |
Vehicle
|
14 days |
Sat 11.02.06 |
Thu 09.03.06 |
Sila |
90% |
| 27 |
Wheel
|
14 days |
Sat 18.02.06 |
Fri 03.03.06 |
Sila |
100% |
| 28 |
Frame
|
26 days |
Wed 01.03.06 |
Sun 26.03.06 |
Ebru |
100% |
| 29 |
Object
|
14 days |
Sat 18.02.06 |
Fri 03.03.06 |
Bahar |
100% |
| 30 |
Road
|
14 days |
Sat 18.02.06 |
Mon 06.03.06 |
Ebru,Cagla |
90% |
| 31 |
Traffic Light
|
14 days |
Sat 18.02.06 |
Fri 03.03.06 |
Kevser |
80% |
| 32 |
Traffic Sign
|
14 days |
Sat 18.02.06 |
Fri 03.03.06 |
Kevser |
100% |
| 33 |
Traffic Model
|
14 days |
Sat 18.02.06 |
Fri 03.03.06 |
Cagla |
95% |
| 34 |
Path
|
14 days |
Sat 18.02.06 |
Fri 17.03.06 |
Sila |
95% |
| 35 |
Integration
|
1 day |
Fri 17.03.06 |
Sat 18.03.06 |
|
0% |
| 36 |
First Dev.
Snapshot Demo
|
0 mins |
Sun 05.03.06 |
Sun 05.03.06 |
|
0% |
| 37 |
GUIEventHandler
Module
|
26 days |
Sat 18.03.06 |
Thu 13.04.06 |
|
83% |
| 38 |
Command
Classes (undoable)
|
26 days |
Sat 18.03.06 |
Thu 13.04.06 |
Ebru |
95% |
| 39 |
Command
Classes (not undoable)
|
26 days |
Sat 18.03.06 |
Thu 13.04.06 |
Bahar |
70% |
| 40 |
0SGWindows
Module
|
49,75 days |
Sun 05.03.06 |
Sun 23.04.06 |
|
74% |
| 41 |
OSGWindows
|
26 days |
Sun 05.03.06 |
Tue 11.04.06 |
Kevser |
80% |
| 42 |
Timeline
|
11 days |
Sat 18.03.06 |
Sun 23.04.06 |
Ebru, Bahar |
95% |
| 43 |
OSGEventHandler
|
26 days |
Sun 05.03.06 |
Tue 11.04.06 |
Kevser |
60% |
| 44 |
AnimationWindow
Module
|
26 days |
Sat 18.03.06 |
Thu 13.04.06 |
|
25% |
| 45 |
AnimationWindow
|
26 days |
Sat 18.03.06 |
Thu 13.04.06 |
Sila, Cagla |
45% |
| 46 |
AnimateEventHandler
|
26 days |
Sat 18.03.06 |
Thu 13.04.06 |
Sila, Cagla |
4% |
| 47 |
PhysicsEngine
Module
|
26 days |
Sat 18.03.06 |
Thu 13.04.06 |
Sila |
95% |
| 48 |
Integration of
Modules
|
7 days |
Thu 13.04.06 |
Thu 20.04.06 |
All |
0% |
| 49 |
Editor Checker
Module
|
14 days |
Thu 20.04.06 |
Thu 04.05.06 |
Sila |
0% |
| 50 |
FileHandler
Module
|
14 days |
Thu 20.04.06 |
Thu 04.05.06 |
Kevser |
0% |
| 51 |
Audio Module
|
14 days |
Thu 20.04.06 |
Thu 04.05.06 |
Ebru |
0% |
| 52 |
Integration of
Modules
|
3 days |
Thu 04.05.06 |
Sun 07.05.06 |
Sila, Ebru, Kevser |
0% |
| 53 |
First Release
and Test Specification
|
0 days |
Sun 23.04.06 |
Sun 23.04.06 |
|
0% |
| 54 |
WP5:
Integration and Verification
|
37 days |
Thu 20.04.06 |
Sat 27.05.06 |
|
0% |
| 55 |
Integration of
Modules
|
6 days |
Mon 24.04.06 |
Sat 29.04.06 |
All |
0% |
| 56 |
Verification
|
37 days |
Thu 20.04.06 |
Sat 27.05.06 |
|
0% |
| 57 |
Test Case
Design
|
15 days |
Thu 20.04.06 |
Fri 05.05.06 |
Bahar, Cagla |
0% |
| 58 |
Test Case
Implementation
|
15 days |
Fri 05.05.06 |
Sat 20.05.06 |
All |
0% |
| 59 |
Run Modular
Tests
|
7 days |
Sat 20.05.06 |
Sat 27.05.06 |
Sila, Ebru,Kevser |
0% |
| 60 |
Run
integration tests
|
7 days |
Sat 20.05.06 |
Sat 27.05.06 |
Bahar, Cagla |
0% |
| 61 |
Presentations
|
5 days |
Sat 22.04.06 |
Wed 26.04.06 |
|
0% |
| 62 |
Preparation of
Presentation Outline
|
5 days |
Sat 22.04.06 |
Wed 26.04.06 |
All |
0% |
| 63 |
Preparation of
Presentation Slides
|
5 days |
Sat 22.04.06 |
Wed 26.04.06 |
All |
0% |
| 64 |
Review
|
5 days |
Mon 22.05.06 |
Fri 26.05.06 |
All |
0% |
| 65 |
Final Demo
|
0 mins |
Sat 27.05.06 |
Sat 27.05.06 |
|
0% |
|