26/03/2006





Project Start:
Project Finish:
Thu 09.02.06
Sat 27.05.06


Living Schedule of C2S


ID
Task Name
Duration Start Finish Resource Names % Complete
1
WP1:Documentation
91 days Thu 09.02.06 Wed 10.05.06   23%
2
Living Schedule
2 days Thu 09.02.06 Fri 10.02.06 All 100%
3
Design Review
2 days Thu 16.02.06 Fri 17.02.06 All 100%
4
Coding Standarts Review
1 day Tue 21.02.06 Tue 21.02.06 All 100%
5
Configuration Management and Development Plan
4 days Tue 21.02.06 Fri 24.02.06 Sila, Ebru, Kevser, Bahar 100%
6
User Manuals
15 days Sat 15.04.06 Sat 29.04.06 All 0%
7
Installation Manual
5 days Sun 30.04.06 Thu 04.05.06 All 0%
8
Release Notes and Software Specifications
6 days Fri 05.05.06 Wed 10.05.06 All 0%
9
Test Specifications
5 days Sat 15.04.06 Wed 19.04.06 All 0%
10
WP2:Detailed Web Page Preperation
3 days Tue 21.02.06 Thu 23.02.06   100%
11
Design of the New Page
1 day Tue 21.02.06 Tue 21.02.06 Cagla 100%
12
Building of the Web Page
1 day Wed 22.02.06 Wed 22.02.06 Cagla 100%
13
Transferring of Old Content to the New Page
1 day Thu 23.02.06 Thu 23.02.06 Cagla 100%
14
WP3:Multimedia Production and GUI Preparation
5 days Sat 11.02.06 Wed 15.02.06   100%
15
Multimedia Production
5 days Sat 11.02.06 Wed 15.02.06   100%
16
Production of Models
5 days Sat 11.02.06 Wed 15.02.06 Sila, Cagla 100%
17
Production of Audio
3 days Mon 13.02.06 Wed 15.02.06 Ebru 100%
18
Graphical User Interface Production
5 days Sat 11.02.06 Wed 15.02.06   100%
19
Menubar
1 day Sat 11.02.06 Sat 11.02.06 Bahar 100%
20
Toolbar
2 days Sun 12.02.06 Mon 13.02.06 Bahar 100%
21
Toolbox
5 days Sat 11.02.06 Wed 15.02.06 Kevser 100%
22
Integration With an OSG Window
2 days Tue 14.02.06 Wed 15.02.06 Ebru 100%
23
WP4: Module Implementation
85,3 days Sat 11.02.06 Sun 07.05.06   50%
24
Fundamental Data Structures
44 days Sat 11.02.06 Sun 26.03.06   74%
25
Camera
26 days Wed 01.03.06 Sun 26.03.06 Bahar 20%
26
Vehicle
14 days Sat 11.02.06 Thu 09.03.06 Sila 90%
27
Wheel
14 days Sat 18.02.06 Fri 03.03.06 Sila 90%
28
Frame
26 days Wed 01.03.06 Sun 26.03.06 Ebru 55%
29
Object
14 days Sat 18.02.06 Fri 03.03.06 Bahar 100%
30
Road
14 days Sat 18.02.06 Mon 06.03.06 Ebru,Cagla 85%
31
Traffic Light
14 days Sat 18.02.06 Fri 03.03.06 Kevser 80%
32
Traffic Sign
14 days Sat 18.02.06 Fri 03.03.06 Kevser 100%
33
Traffic Model
14 days Sat 18.02.06 Fri 03.03.06 Cagla 95%
34
Path
14 days Sat 18.02.06 Fri 17.03.06 Sila 95%
35
Integration
1 day Fri 17.03.06 Sat 18.03.06   100%
36
First Dev. Snapshot Demo
0 mins Sun 05.03.06 Sun 05.03.06   100%
37
GUIEventHandler Module
26 days Sat 18.03.06 Thu 13.04.06   44%
38
Command Classes (undoable)
26 days Sat 18.03.06 Thu 13.04.06 Ebru 70%
39
Command Classes (not undoable)
26 days Sat 18.03.06 Thu 13.04.06 Bahar 18%
40
0SGWindows Module
49,75 days Sun 05.03.06 Sun 23.04.06   57%
41
OSGWindows
26 days Sun 05.03.06 Tue 11.04.06 Kevser 60%
42
Timeline
11 days Sat 18.03.06 Sun 23.04.06 Ebru, Bahar 90%
43
OSGEventHandler
26 days Sun 05.03.06 Tue 11.04.06 Kevser 40%
44
AnimationWindow Module
26 days Sat 18.03.06 Thu 13.04.06   4%
45
AnimationWindow
26 days Sat 18.03.06 Thu 13.04.06 Sila, Cagla 7%
46
AnimateEventHandler
26 days Sat 18.03.06 Thu 13.04.06 Sila, Cagla 0%
47
PhysicsEngine Module
26 days Sat 18.03.06 Thu 13.04.06 Sila 80%
48
Integration of Modules
7 days Thu 13.04.06 Thu 20.04.06 All 0%
49
Editor Checker Module
14 days Thu 20.04.06 Thu 04.05.06 Sila 0%
50
FileHandler Module
14 days Thu 20.04.06 Thu 04.05.06 Kevser 0%
51
Audio Module
14 days Thu 20.04.06 Thu 04.05.06 Ebru 0%
52
Integration of Modules
3 days Thu 04.05.06 Sun 07.05.06 Sila, Ebru, Kevser 0%
53
First Release and Test Specification
0 days Sun 23.04.06 Sun 23.04.06   0%
54
WP5: Integration and Verification
37 days Thu 20.04.06 Sat 27.05.06   0%
55
Integration of Modules
6 days Mon 24.04.06 Sat 29.04.06 All 0%
56
Verification
37 days Thu 20.04.06 Sat 27.05.06   0%
57
Test Case Design
15 days Thu 20.04.06 Fri 05.05.06 Bahar, Cagla 0%
58
Test Case Implementation
15 days Fri 05.05.06 Sat 20.05.06 All 0%
59
Run Modular Tests
7 days Sat 20.05.06 Sat 27.05.06 Sila, Ebru,Kevser 0%
60
Run integration tests
7 days Sat 20.05.06 Sat 27.05.06 Bahar, Cagla 0%
61
Presentations
5 days Sat 22.04.06 Wed 26.04.06   0%
62
Preparation of Presentation Outline
5 days Sat 22.04.06 Wed 26.04.06 All 0%
63
Preparation of Presentation Slides
5 days Sat 22.04.06 Wed 26.04.06 All 0%
64
Review
5 days Mon 22.05.06 Fri 26.05.06 All 0%
65
Final Demo
0 mins Sat 27.05.06 Sat 27.05.06   0%