Date: 23.04.06



Project Start:
Project Finish:
Mon 10/24/05
Mon 5/29/06

Tasks of CoreAccess


ID
Task Name
DurationStartFinishResource Names% Complete
1
Management of the Project
90 daysThu 2/2/06Fri 5/26/06 90%
2
Initial content setup
2 daysThu 2/9/06Fri 2/10/06Mustafa100%
3
Transfering webpage to web area
1 dayFri 2/10/06Fri 2/10/06Mustafa100%
4
Updating Web Page
90 daysThu 2/2/06Fri 5/26/06Mustafa90%
5
Adding Progress Reports
90 daysThu 2/2/06Fri 5/26/06Mustafa90%
6
Setup CVS for CoreAccess
6 daysMon 2/13/06Wed 2/22/06All100%
7
Setup Bugzilla for the project
6 daysMon 2/20/06Thu 3/2/06All15%
8
Configuration Management and Development Plan
5 daysThu 2/9/06Tue 2/14/06All100%
9
Implementation Plan Specification
9 daysWed 2/8/06Fri 2/17/06All100%
10
Test Plan Specification
11 daysTue 2/21/06Mon 3/6/06All100%
11
Development of the Project
99 daysTue 1/24/06Mon 5/29/06 56%
12
Implementation of Modules
69 daysWed 1/25/06Mon 4/24/06 68%
13
GPS Module Implementation
10 daysTue 2/21/06Sat 3/4/06 50%
14
Implementing Virtual GPS
10 daysTue 2/21/06Sat 3/4/06Mustafa50%
15
Milestone
0 daysSat 3/4/06Sat 3/4/06Mustafa0%
16
PDA Module Implementation
49 daysWed 1/25/06Wed 3/29/06 97%
17
User Interface Design in PDA (C# . net)
25 daysWed 1/25/06Sun 2/26/06Mehmet95%
18
Implementing Language Manager
5 daysMon 2/20/06Sun 2/26/06Mehmet90%
19
Map Manipulation and Storage on PDA
32 daysFri 2/10/06Wed 3/29/06Mehmet;Mustafa;Eda100%
20
Milestone
0 daysWed 3/29/06Wed 3/29/06Mehmet;Mustafa;Eda0%
21
Content Manager Module Implementation
27 daysMon 2/13/06Fri 3/17/06 90%
22
Adding functionality of Add/Remove Nodes
25 daysMon 2/13/06Wed 3/15/06Eda90%
23
Enhancement of User Interfaces
20 daysTue 2/21/06Fri 3/17/06Eda90%
24
Milestone
0 daysWed 3/15/06Wed 3/15/06Eda0%
25
Server Side Implementation
61 daysMon 2/6/06Mon 4/24/06 51%
26
GIS Engine Module
33 daysMon 2/6/06Fri 3/17/06 53%
27
Graph Generation for Path Finding
21 daysMon 2/6/06Thu 3/2/06Mehmet; Mustafa70%
28
Matching the Nodes with Map Labels
6 daysTue 2/28/06Mon 3/6/06Mehmet; Mustafa80%
29
Combining the Results of PathFinder and Transportation
10 daysMon 3/6/06Fri 3/17/06Mehmet; Mustafa0%
30
Activity Module
15 daysMon 2/20/06Thu 3/9/06 91%
31
Creating Activity Database
10 daysMon 2/20/06Fri 3/3/06Sercan100%
32
Filling Activity Database
6 daysFri 3/3/06Thu 3/9/06Sercan75%
33
Pathfinder Module
18 daysMon 3/20/06Wed 4/12/06 47%
34
Implementation of Dijkstra's Algorithm
10 daysMon 3/20/06Fri 3/31/06Eda45%
35
Providing Links between Nodes
5 daysThu 4/6/06Wed 4/12/06Eda50%
36
Transportation Module
19 daysMon 3/20/06Thu 4/13/06 10%
37
Adding Vehicle Support
10 daysMon 3/20/06Fri 3/31/06Onur30%
38
Time Estimation Support
10 daysFri 3/24/06Thu 4/6/06Onur0%
39
Cost Estimation Support
10 daysFri 3/31/06Thu 4/13/06Onur0%
40
Milestone (First Release)
0 daysMon 4/10/06Mon 4/10/06Onur0%
41
Ontology Module
13 daysMon 4/10/06Mon 4/24/06 27%
42
Developing Cinema Ontology
8 daysMon 4/10/06Wed 4/19/06Eda; Mehmet55%
43
Developing Transportation Ontology
8 daysMon 4/17/06Mon 4/24/06Eda; Mehmet25%
44
Reasoning on Ontology
8 daysMon 4/10/06Wed 4/19/06Eda; Mehmet0%
45
Logger Module
12 daysMon 3/27/06Tue 4/11/06 49%
46
Storing Coming Information into DB
8 daysMon 3/27/06Wed 4/5/06Sercan75%
47
Adding Graphical Display
7 daysMon 4/3/06Tue 4/11/06Sercan20%
48
Administrative Module
17 daysMon 3/13/06Tue 4/4/06 69%
49
Adding Map Editing Option
9 daysMon 3/13/06Thu 3/23/06Eda100%
50
Adding Management Property of CM Accounts
8 daysMon 3/20/06Wed 3/29/06Eda60%
51
Developing Statistics Screen
7 daysMon 3/27/06Tue 4/4/06Eda40%
52
Map Module
14 daysMon 3/20/06Thu 4/6/06 95%
53
Forming Vector Map
8 daysMon 3/20/06Wed 3/29/06Mehmet; Mustafa100%
54
Defining Activity Places on Map
9 daysMon 3/27/06Thu 4/6/06Mehmet; Mustafa90%
55
Milestone
0 daysMon 4/10/06Mon 4/10/06Mehmet; Mustafa0%
56
Database Module Implementation
15 daysMon 2/20/06Thu 3/9/06 96%
57
Defining Schema of DB
6 daysMon 2/20/06Mon 2/27/06Onur;Sercan100%
58
Writing SQL Statements
5 daysMon 2/27/06Fri 3/3/06Onur;Sercan100%
59
Implementing DB Component
7 daysThu 3/2/06Thu 3/9/06Onur;Sercan90%
60
Integration of Modules
32 daysWed 4/12/06Thu 5/18/06 39%
61
GPS Receiver - PDA Interaction
25 daysWed 4/12/06Wed 5/10/06All0%
62
Server Modules Integration
25 daysWed 4/12/06Wed 5/10/06All70%
63
Database- Server Connection
27 daysWed 4/12/06Fri 5/12/06All100%
64
Integration of Logger Module
27 daysWed 4/19/06Thu 5/18/06All55%
65
Integration of Ontology Module
26 daysThu 4/20/06Thu 5/18/06All0%
66
Integration of PathFinder to Map
27 daysWed 4/19/06Thu 5/18/06All25%
67
Integration of Transportation to Map
26 daysThu 4/20/06Thu 5/18/06All20%
68
Milestone
0 daysThu 5/18/06Thu 5/18/06All0%
69
Testing the System
99 daysTue 1/24/06Mon 5/29/06 51%
70
Implementation Alpha Testing
94 daysTue 1/24/06Tue 5/23/06All70%
71
Integration Alpha Testing
27 daysWed 4/19/06Thu 5/18/06All35%
72
Beta Testing
27 daysThu 4/27/06Mon 5/29/06All0%
73
Documentation Support
13 daysMon 5/8/06Tue 5/23/06 0%
74
Taking Snapshots
1 dayMon 5/8/06Mon 5/8/06All0%
75
Installation Guide
5 daysThu 5/11/06Tue 5/16/06Eda;Sercan0%
76
User Manual
8 daysTue 5/9/06Wed 5/17/06Onur;Sercan0%
77
Help Documentation
5 daysMon 5/15/06Fri 5/19/06Mehmet; Mustafa0%
78
Milestone
3 daysFri 5/19/06Tue 5/23/06All0%