ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
1 | Management of the Project | 90 days | Thu 2/2/06 | Fri 5/26/06 | | 90% |
2 | Initial content setup | 2 days | Thu 2/9/06 | Fri 2/10/06 | Mustafa | 100% |
3 | Transfering webpage to web area | 1 day | Fri 2/10/06 | Fri 2/10/06 | Mustafa | 100% |
4 | Updating Web Page | 90 days | Thu 2/2/06 | Fri 5/26/06 | Mustafa | 90% |
5 | Adding Progress Reports | 90 days | Thu 2/2/06 | Fri 5/26/06 | Mustafa | 90% |
6 | Setup CVS for CoreAccess | 6 days | Mon 2/13/06 | Wed 2/22/06 | All | 100% |
7 | Setup Bugzilla for the project | 6 days | Mon 2/20/06 | Thu 3/2/06 | All | 15% |
8 | Configuration Management and Development Plan | 5 days | Thu 2/9/06 | Tue 2/14/06 | All | 100% |
9 | Implementation Plan Specification | 9 days | Wed 2/8/06 | Fri 2/17/06 | All | 100% |
10 | Test Plan Specification | 11 days | Tue 2/21/06 | Mon 3/6/06 | All | 100% |
11 | Development of the Project | 99 days | Tue 1/24/06 | Mon 5/29/06 | | 56% |
12 | Implementation of Modules | 69 days | Wed 1/25/06 | Mon 4/24/06 | | 68% |
13 | GPS Module Implementation | 10 days | Tue 2/21/06 | Sat 3/4/06 | | 50% |
14 | Implementing Virtual GPS | 10 days | Tue 2/21/06 | Sat 3/4/06 | Mustafa | 50% |
15 | Milestone | 0 days | Sat 3/4/06 | Sat 3/4/06 | Mustafa | 0% |
16 | PDA Module Implementation | 49 days | Wed 1/25/06 | Wed 3/29/06 | | 97% |
17 | User Interface Design in PDA (C# . net) | 25 days | Wed 1/25/06 | Sun 2/26/06 | Mehmet | 95% |
18 | Implementing Language Manager | 5 days | Mon 2/20/06 | Sun 2/26/06 | Mehmet | 90% |
19 | Map Manipulation and Storage on PDA | 32 days | Fri 2/10/06 | Wed 3/29/06 | Mehmet;Mustafa;Eda | 100% |
20 | Milestone | 0 days | Wed 3/29/06 | Wed 3/29/06 | Mehmet;Mustafa;Eda | 0% |
21 | Content Manager Module Implementation | 27 days | Mon 2/13/06 | Fri 3/17/06 | | 90% |
22 | Adding functionality of Add/Remove Nodes | 25 days | Mon 2/13/06 | Wed 3/15/06 | Eda | 90% |
23 | Enhancement of User Interfaces | 20 days | Tue 2/21/06 | Fri 3/17/06 | Eda | 90% |
24 | Milestone | 0 days | Wed 3/15/06 | Wed 3/15/06 | Eda | 0% |
25 | Server Side Implementation | 61 days | Mon 2/6/06 | Mon 4/24/06 | | 51% |
26 | GIS Engine Module | 33 days | Mon 2/6/06 | Fri 3/17/06 | | 53% |
27 | Graph Generation for Path Finding | 21 days | Mon 2/6/06 | Thu 3/2/06 | Mehmet; Mustafa | 70% |
28 | Matching the Nodes with Map Labels | 6 days | Tue 2/28/06 | Mon 3/6/06 | Mehmet; Mustafa | 80% |
29 | Combining the Results of PathFinder and Transportation | 10 days | Mon 3/6/06 | Fri 3/17/06 | Mehmet; Mustafa | 0% |
30 | Activity Module | 15 days | Mon 2/20/06 | Thu 3/9/06 | | 91% |
31 | Creating Activity Database | 10 days | Mon 2/20/06 | Fri 3/3/06 | Sercan | 100% |
32 | Filling Activity Database | 6 days | Fri 3/3/06 | Thu 3/9/06 | Sercan | 75% |
33 | Pathfinder Module | 18 days | Mon 3/20/06 | Wed 4/12/06 | | 47% |
34 | Implementation of Dijkstra's Algorithm | 10 days | Mon 3/20/06 | Fri 3/31/06 | Eda | 45% |
35 | Providing Links between Nodes | 5 days | Thu 4/6/06 | Wed 4/12/06 | Eda | 50% |
36 | Transportation Module | 19 days | Mon 3/20/06 | Thu 4/13/06 | | 10% |
37 | Adding Vehicle Support | 10 days | Mon 3/20/06 | Fri 3/31/06 | Onur | 30% |
38 | Time Estimation Support | 10 days | Fri 3/24/06 | Thu 4/6/06 | Onur | 0% |
39 | Cost Estimation Support | 10 days | Fri 3/31/06 | Thu 4/13/06 | Onur | 0% |
40 | Milestone (First Release) | 0 days | Mon 4/10/06 | Mon 4/10/06 | Onur | 0% |
41 | Ontology Module | 13 days | Mon 4/10/06 | Mon 4/24/06 | | 27% |
42 | Developing Cinema Ontology | 8 days | Mon 4/10/06 | Wed 4/19/06 | Eda; Mehmet | 55% |
43 | Developing Transportation Ontology | 8 days | Mon 4/17/06 | Mon 4/24/06 | Eda; Mehmet | 25% |
44 | Reasoning on Ontology | 8 days | Mon 4/10/06 | Wed 4/19/06 | Eda; Mehmet | 0% |
45 | Logger Module | 12 days | Mon 3/27/06 | Tue 4/11/06 | | 49% |
46 | Storing Coming Information into DB | 8 days | Mon 3/27/06 | Wed 4/5/06 | Sercan | 75% |
47 | Adding Graphical Display | 7 days | Mon 4/3/06 | Tue 4/11/06 | Sercan | 20% |
48 | Administrative Module | 17 days | Mon 3/13/06 | Tue 4/4/06 | | 69% |
49 | Adding Map Editing Option | 9 days | Mon 3/13/06 | Thu 3/23/06 | Eda | 100% |
50 | Adding Management Property of CM Accounts | 8 days | Mon 3/20/06 | Wed 3/29/06 | Eda | 60% |
51 | Developing Statistics Screen | 7 days | Mon 3/27/06 | Tue 4/4/06 | Eda | 40% |
52 | Map Module | 14 days | Mon 3/20/06 | Thu 4/6/06 | | 95% |
53 | Forming Vector Map | 8 days | Mon 3/20/06 | Wed 3/29/06 | Mehmet; Mustafa | 100% |
54 | Defining Activity Places on Map | 9 days | Mon 3/27/06 | Thu 4/6/06 | Mehmet; Mustafa | 90% |
55 | Milestone | 0 days | Mon 4/10/06 | Mon 4/10/06 | Mehmet; Mustafa | 0% |
56 | Database Module Implementation | 15 days | Mon 2/20/06 | Thu 3/9/06 | | 96% |
57 | Defining Schema of DB | 6 days | Mon 2/20/06 | Mon 2/27/06 | Onur;Sercan | 100% |
58 | Writing SQL Statements | 5 days | Mon 2/27/06 | Fri 3/3/06 | Onur;Sercan | 100% |
59 | Implementing DB Component | 7 days | Thu 3/2/06 | Thu 3/9/06 | Onur;Sercan | 90% |
60 | Integration of Modules | 32 days | Wed 4/12/06 | Thu 5/18/06 | | 39% |
61 | GPS Receiver - PDA Interaction | 25 days | Wed 4/12/06 | Wed 5/10/06 | All | 0% |
62 | Server Modules Integration | 25 days | Wed 4/12/06 | Wed 5/10/06 | All | 70% |
63 | Database- Server Connection | 27 days | Wed 4/12/06 | Fri 5/12/06 | All | 100% |
64 | Integration of Logger Module | 27 days | Wed 4/19/06 | Thu 5/18/06 | All | 55% |
65 | Integration of Ontology Module | 26 days | Thu 4/20/06 | Thu 5/18/06 | All | 0% |
66 | Integration of PathFinder to Map | 27 days | Wed 4/19/06 | Thu 5/18/06 | All | 25% |
67 | Integration of Transportation to Map | 26 days | Thu 4/20/06 | Thu 5/18/06 | All | 20% |
68 | Milestone | 0 days | Thu 5/18/06 | Thu 5/18/06 | All | 0% |
69 | Testing the System | 99 days | Tue 1/24/06 | Mon 5/29/06 | | 51% |
70 | Implementation Alpha Testing | 94 days | Tue 1/24/06 | Tue 5/23/06 | All | 70% |
71 | Integration Alpha Testing | 27 days | Wed 4/19/06 | Thu 5/18/06 | All | 35% |
72 | Beta Testing | 27 days | Thu 4/27/06 | Mon 5/29/06 | All | 0% |
73 | Documentation Support | 13 days | Mon 5/8/06 | Tue 5/23/06 | | 0% |
74 | Taking Snapshots | 1 day | Mon 5/8/06 | Mon 5/8/06 | All | 0% |
75 | Installation Guide | 5 days | Thu 5/11/06 | Tue 5/16/06 | Eda;Sercan | 0% |
76 | User Manual | 8 days | Tue 5/9/06 | Wed 5/17/06 | Onur;Sercan | 0% |
77 | Help Documentation | 5 days | Mon 5/15/06 | Fri 5/19/06 | Mehmet; Mustafa | 0% |
78 | Milestone | 3 days | Fri 5/19/06 | Tue 5/23/06 | All | 0% |