ID | Task_Name | Duration | Start_Date | Finish | Resource_Names | Percent_Complete |
---|---|---|---|---|---|---|
1 | Web Page Preperation | 7 days | Tue 14.02.06 | Wed 22.02.06 | Serhat | 100% |
2 | Review of other design report | 3 days | Wed 01.02.06 | Fri 03.02.06 | All Members | 100% |
3 | Configuration Management and Development Plan | 10 days | Wed 01.02.06 | Tue 14.02.06 | All Members | 100% |
4 | Coding | 59 days | Wed 01.02.06 | Wed 19.04.06 | 13% | |
5 | Simulator Implementation | 18 days | Wed 01.02.06 | Thu 23.02.06 | All Members | 30% |
6 | GUI Implementation | 4 days | Tue 14.02.06 | Sun 19.02.06 | Selçuk, Serhat | 55% |
7 | Drawing Implementation | 5 days | Tue 21.02.06 | Sun 26.02.06 | Selçuk, İlknur | 60% |
8 | First Dev. Snapshot demo | 1 day | Wed 01.03.06 | Wed 01.03.06 | 0% | |
9 | Simulator-GUI-Drawing Integration | 8 days | Mon 27.02.06 | Wed 08.03.06 | All Members | 0% |
10 | Edit/Zoom Implementation | 2 days | Wed 08.03.06 | Thu 09.03.06 | Selçuk, İlknur | 60% |
11 | File Type Implementation | 4 days | Mon 20.02.06 | Thu 23.02.06 | Serhat, Gökhan | 0% |
12 | Library Implementation | 6 days | Fri 24.02.06 | Thu 02.03.06 | Gökhan, Hüseyin | 0% |
13 | Import/Export Diglog File Implementation | 4 days | Fri 24.02.06 | Tue 28.02.06 | Serhat, İlknur | 0% |
14 | Printing Implementation | 4 days | Sat 25.02.06 | Wed 01.03.06 | Gökhan, İlknur | 0% |
15 | Scripting Implementation | 16 days | Tue 28.02.06 | Tue 21.03.06 | Gökhan, Hüseyin | 0% |
16 | Error Detection Implementation | 10 days | Tue 14.03.06 | Mon 27.03.06 | Gökhan, Hüseyin, Selçuk | 0% |
17 | System Integration | 7 days | Tue 28.03.06 | Wed 05.04.06 | All Members | 0% |
18 | First Release and Test Spec. | 1 day | Wed 19.04.06 | Wed 19.04.06 | 0% | |
19 | Testing | 51 days | Mon 20.02.06 | Thu 27.04.06 | 0% | |
20 | Simulator Unit Testing | 4 days | Sat 25.02.06 | Wed 01.03.06 | Selçuk, Hüseyin | 0% |
21 | GUI and Drawing Unit Testing | 4 days | Mon 20.02.06 | Thu 23.02.06 | Selçuk, Gökhan, İlknur | 0% |
22 | Scripting Unit Testing | 4 days | Wed 22.03.06 | Mon 27.03.06 | Serhat, Hüseyin | 0% |
23 | File Operations/Library Unit Testing | 4 days | Thu 02.03.06 | Tue 07.03.06 | Serhat, Gökhan, İlknur | 0% |
24 | Error Detection Unit Testing | 4 days | Tue 28.03.06 | Fri 31.03.06 | Hüseyin, Gökhan, İlknur | 0% |
25 | Simulator-GUI-Drawing Integration Testing | 4 days | Thu 09.03.06 | Tue 14.03.06 | Serhat, Selçuk, Hüseyin | 0% |
26 | System Integration Testing | 7 days | Thu 06.04.06 | Fri 14.04.06 | Gökhan, Hüseyin, Selçuk | 0% |
27 | Whole System Test | 10 days | Sat 15.04.06 | Thu 27.04.06 | All Members | 0% |
28 | Help/User Manual Preperation | 4 days | Wed 12.04.06 | Sat 15.04.06 | Gökhan, Serhat, Hüseyin | 0% |
29 | Final Demo/Competition | 1 day? | Tue 23.05.06 | Tue 23.05.06 | 0% |