MindGate

Company: MindUs
Start: January 2, 2006
Finish: June 5, 2006
Phase: Implementation
Report Date: February 9, 2006

Gantt Chart

WBS Name Work Week 1, 2006 Week 2, 2006 Week 3, 2006 Week 4, 2006 Week 5, 2006 Week 6, 2006 Week 7, 2006 Week 8, 2006 Week 9, 2006 Week 10, 2006 Week 11, 2006 Week 12, 2006 Week 13, 2006 Week 14, 2006 Week 15, 2006 Week 16, 2006 Week 17, 2006 Week 18, 2006 Week 19, 2006 Week 20, 2006 Week 21, 2006 Week 22, 2006
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5
1 Prototype Implemetation 12d 5h
1.1 Prototype Scope 2d
1.2 Rapid Protoype Implementation 9d
1.3 Prototype Testing 1d
1.4 Prototype Demonstration 5h
2 Module Implementation 50d
2.1 ConnectionControl Implementation 43d
2.1.1 ConnectionControl Design Revision 3d
2.1.2 ConnectionControl Core Implementation 35d
2.1.3 ConnectionControl Proxy Integration 15d
2.1.4 ConnectionControl Module Testing 5d
2.2 DatabaseControl Implementation 43d
2.2.1 DatabaseControl Design Revision 3d
2.2.2 Database Control Core Implementation 35d
2.2.3 Database Control Module Testing 5d
2.3 Categorizer Implementation 50d
2.3.1 Categorizer Design Revision 5d
2.3.2 Categorizer Core Implementation 35d
2.3.3 Categorizer Html Parser Integration 10d
2.3.4 Categorizer Testing 5d
2.3.5 Categorizer Corpus Collection 5d
2.3.6 Categorizer Accuracy Testing 5d
2.4 InterfaceControl Implementation 43d
2.4.1 InterfaceControl Design Revision 3d
2.4.2 InterfaceControl Core Implementation 35d
2.4.3 InterfaceControl WebServer Integration 15d
2.4.4 InterfaceControl Module Testing 5d
2.4.5 GUI Implementation 15d
3 Module Integration 25d
4 Integration Testing 15d
5 Categorizer Training 15d
6 Deployment Documention 15d
7 Deployment Packaging 15d
8 Final Tesing 15d

Tasks

WBS Name Start Finish Work Priority Complete Cost Notes
1 Prototype Implemetation Jan 2 Jan 16 12d 5h
1.1 Prototype Scope Jan 2 Jan 3 2d 100%
1.2 Rapid Protoype Implementation Jan 4 Jan 13 9d 100%
1.3 Prototype Testing Jan 14 Jan 14 1d 100%
1.4 Prototype Demonstration Jan 16 Jan 16 5h 100%
2 Module Implementation Jan 16 Mar 15 50d
2.1 ConnectionControl Implementation Jan 16 Mar 7 43d
2.1.1 ConnectionControl Design Revision Jan 16 Jan 19 3d 100%
2.1.2 ConnectionControl Core Implementation Jan 19 Mar 1 35d 0%
2.1.3 ConnectionControl Proxy Integration Jan 19 Feb 6 15d 0%
2.1.4 ConnectionControl Module Testing Mar 1 Mar 7 5d 0%
2.2 DatabaseControl Implementation Jan 16 Mar 7 43d
2.2.1 DatabaseControl Design Revision Jan 16 Jan 19 3d 100%
2.2.2 Database Control Core Implementation Jan 19 Mar 1 35d 0%
2.2.3 Database Control Module Testing Mar 1 Mar 7 5d 0%
2.3 Categorizer Implementation Jan 16 Mar 15 50d
2.3.1 Categorizer Design Revision Jan 16 Jan 21 5d 100%
2.3.2 Categorizer Core Implementation Jan 21 Mar 3 35d 0%
2.3.3 Categorizer Html Parser Integration Jan 21 Feb 2 10d 0%
2.3.4 Categorizer Testing Mar 3 Mar 9 5d 0%
2.3.5 Categorizer Corpus Collection Mar 3 Mar 9 5d 0%
2.3.6 Categorizer Accuracy Testing Mar 9 Mar 15 5d 0%
2.4 InterfaceControl Implementation Jan 16 Mar 7 43d
2.4.1 InterfaceControl Design Revision Jan 16 Jan 19 3d 100%
2.4.2 InterfaceControl Core Implementation Jan 19 Mar 1 35d 0%
2.4.3 InterfaceControl WebServer Integration Jan 24 Feb 10 15d 0%
2.4.4 InterfaceControl Module Testing Mar 1 Mar 7 5d 0%
2.4.5 GUI Implementation Feb 10 Feb 28 15d 0%
3 Module Integration Mar 15 Apr 13 25d 0%
4 Integration Testing Apr 13 May 1 15d 0% Sat 07 Jan 2006, 21:57
5 Categorizer Training Mar 15 Apr 1 15d 0%
6 Deployment Documention May 1 May 18 15d 0%
7 Deployment Packaging May 1 May 18 15d 0%
8 Final Tesing May 18 Jun 5 15d 0%

Resources

Name Short name Type Group Email Cost
Berkan Work 0
Kerim Work 0
Ozgur Work 0
Tolga Work 0