ULApag




Project Start:
Project Finish:
Sun 12.02.06
Thu 27.07.06


Tasks

ID Task Name Duration Start Finish Resource Names % Complete
1 Documentation 30 days Mon 13.02.06 Fri 24.03.06   100%
2 Living Schedule 2 days Fri 10.02.06 Mon 13.02.06 all 100%
3 User Manuals 10 days Mon 17.04.06 Fri 28.04.06 all 100%
4 Installation Manual 10 days Mon 01.05.06 Fri 12.05.06 sinan 100%
5 Release Notes and Software Specifications 9 days Mon 15.05.06 Thu 25.05.06 sinan 100%
6 Module Development 70 days Fri 21.04.06 Thu 27.07.06   100%
7 Library Implementation 6 days Wed 15.02.06 Wed 22.02.06 cagatay;ercan 100%
8 Sound Manager Implementation 5 days Mon 20.02.06 Fri 24.02.06 selcuk 100%
9 Text Manager Implementation 1 day Mon 27.02.06 Mon 27.02.06 sinan 100%
10 Scene Class Implementation 14 days Mon 27.02.06 Thu 16.03.06 selcuk;cagatay 100%
11 Frame Class Implementation 12 days Thu 16.03.06 Fri 31.03.06 cagatay;selcuk 100%
12 Timeline Implementation 6 days Thu 16.03.06 Thu 23.03.06 sinan;ercan 100%
13 Event Handler Implementation 8 days Wed 22.02.06 Fri 03.03.06 all 100%
14 User Interface 5 days Mon 27.03.06 Fri 31.03.06 sinan;ercan 100%
15 File Organization 5 days Mon 03.04.06 Fri 07.04.06 all 100%
16 Run-Time-Environment Implementation 14 days Mon 03.04.06 Thu 20.04.06 ercan;cagatay 100%
17 Verification 40 days Mon 13.02.06 Fri 07.04.06   100%
18 Test Case Design 7 days Tue 04.04.06 Wed 12.04.06 all 100%
19 Test Case Implementation 8 days Wed 12.04.06 Fri 21.04.06 all 100%
20 First release and Test Specification 0 days Fri 21.04.06 Fri 21.04.06 all 100%
21 Presentations 3 days Mon 13.02.06 Wed 15.02.06   100%
22 Preparation of Presentation Slides 2 days Wed 24.05.06 Thu 25.05.06 all 100%
23 Final Demo 1 day Fri 26.05.06 Wed 31.05.06 all 100%

Resources

ID Name Max Units
1 cagatay 100%
2 ercan 100%
3 sinan 100%
4 selcuk 100%

Assignments

Task ID Task Name Resource Name Work Start Finish % Work Complete
2 Living Schedule all 16 hrs Fri 10.02.06 Mon 13.02.06 100%
3 User Manuals all 80 hrs Mon 17.04.06 Fri 28.04.06 100%
4 Installation Manual sinan 80 hrs Mon 01.05.06 Fri 12.05.06 100%
5 Release Notes and Software Specifications sinan 72 hrs Mon 15.05.06 Thu 25.05.06 100%
7 Library Implementation cagatay 48 hrs Wed 15.02.06 Wed 22.02.06 100%
7 Library Implementation ercan 48 hrs Wed 15.02.06 Wed 22.02.06 100%
8 Sound Manager Implementation selcuk 40 hrs Mon 20.02.06 Fri 24.02.06 100%
9 Text Manager Implementation sinan 8 hrs Mon 27.02.06 Mon 27.02.06 100%
10 Scene Class Implementation selcuk 112 hrs Mon 27.02.06 Thu 16.03.06 100%
10 Scene Class Implementation cagatay 112 hrs Mon 27.02.06 Thu 16.03.06 100%
11 Frame Class Implementation cagatay 96 hrs Thu 16.03.06 Fri 31.03.06 100%
11 Frame Class Implementation selcuk 96 hrs Thu 16.03.06 Fri 31.03.06 100%
12 Timeline Implementation sinan 48 hrs Thu 16.03.06 Thu 23.03.06 100%
12 Timeline Implementation ercan 48 hrs Thu 16.03.06 Thu 23.03.06 100%
13 Event Handler Implementation all 64 hrs Wed 22.02.06 Fri 03.03.06 100%
14 User Interface sinan 40 hrs Mon 27.03.06 Fri 31.03.06 100%
14 User Interface ercan 40 hrs Mon 27.03.06 Fri 31.03.06 100%
15 File Organization all 40 hrs Mon 03.04.06 Fri 07.04.06 100%
16 Run-Time-Environment Implementation ercan 112 hrs Mon 03.04.06 Thu 20.04.06 100%
16 Run-Time-Environment Implementation cagatay 112 hrs Mon 03.04.06 Thu 20.04.06 100%
18 Test Case Design all 56 hrs Tue 04.04.06 Wed 12.04.06 100%
19 Test Case Implementation all 64 hrs Wed 12.04.06 Fri 21.04.06 100%
20 First release and Test Specification all 0 hrs Fri 21.04.06 Fri 21.04.06 100%
22 Preparation of Presentation Slides all 16 hrs Wed 24.05.06 Thu 25.05.06 100%
23 Final Demo all 8 hrs Wed 31.05.06 Fri 26.05.06 100%

HOME