Task

Duration

Start

Finish

Assigned To

Status

Configuration Management Planning

4 days

9 February

12 February

All Members

%100

Design & Demo Review

6 days

9 February

14 February

All Members

%60

Web Page Design

8 days

13 February

21 February Gürkan Caner Birer

%0

Other Group's Design Review

4 days

15 February

18 February

All Members

%0

Coding

85 days

1 February

23 April

All Members

%10

Creating Virtual World with ODE

 28 days

10 February

10 March

Kadir Kuz

%2

AR Toolkit C# Integration DEMO

10 days

3 February

13 February

Mustafa Ayan

%87

AR Toolkit ODE Integration DEMO

15 days

1 February

16 February

Mustafa Ayan

%90

Creating ARToolkit API

20 days 13 February

2 March

Münir Ercan

%0

Creating .Net Based Independent Classes 17 days 3 March 20 March

Münir Ercan

%0

Creating GUI 1.0

10 days

1 February

13 February

Gürkan Caner Birer

%90

Creating GUI 1.1

20 days

28 February

19 March

Gürkan Caner Birer

%0

Integrating ODE with OpenGL DEMO

10 days

15 March

25 March

Mustafa Ayan

%0

Scenario Creation

10 days

10 March

20 March

Kadir Kuz

Münir Ercan

%0

Integration 15 days 20 March 4 April All Members %0

Testing

35 days

20 March

26 April

All Members

%0

Unit Testing 1

5 days

20 March

24 March

Kadir Kuz

Münir Ercan

%0

Unit Testing 2

5 days

24 March

28 March

Gürkan Caner Birer

Mustafa Ayan

%0

Unit Testing 3

5 days

30 March

4 April

All Members

%0

Integration Testing

10 days

5 April

15 April

All Members

%0

System Validation

10 days

16 April

26 April

All Members

%0

Preparation of User Manuals

10 days

2 May

11 May

All Members

%0