Company: | I2Tech |
Start: | February 26, 2007 |
Finish: | June 10, 2007 |
Report Date: | April 4, 2007 |
|
|
WBS | Name | Start | Finish | Complete |
---|---|---|---|---|
1 | Implementation of PosterInBlue | Feb 26 | Jun 10 | |
1.1 | Bluetooth Module | Feb 26 | Apr 30 | |
1.1.1 | Connection and Device Discovery | Feb 26 | Mar 11 | 100% |
1.1.2 | Sending text file | Mar 12 | Mar 14 | 100% |
1.1.3 | Sending V-Card | Mar 15 | Mar 24 | 0% |
1.1.4 | Sending images | Mar 20 | Mar 31 | 100% |
1.1.5 | Testing | Apr 1 | Apr 21 | 0% |
1.1.6 | Finalizing Bluetooth module | Apr 22 | Apr 30 | 0% |
1.2 | FPGA Module | Feb 26 | Apr 30 | |
1.2.1 | Configuration format desicion | Feb 26 | Mar 11 | 80% |
1.2.2 | Hardware Design for configuration | Mar 12 | Apr 8 | |
1.2.2.1 | Multiple image display | Mar 12 | Mar 16 | 100% |
1.2.2.2 | Poster duration design | Mar 17 | Mar 23 | 60% |
1.2.2.3 | Designing AT Command Generator | Mar 24 | Apr 8 | 0% |
1.2.3 | Testing | Apr 8 | Apr 21 | 0% |
1.2.4 | Finalizing FPGA Module | Apr 22 | Apr 30 | 0% |
1.3 | Admin tool Module | Mar 11 | Apr 30 | |
1.3.1 | Conf File Preparation | Mar 11 | Mar 24 | 80% |
1.3.2 | Sending Conf file over Bluetooth | Mar 25 | Apr 7 | 0% |
1.3.3 | Testing | Apr 8 | Apr 21 | 0% |
1.3.4 | Finalizing Admin tool module | Apr 22 | Apr 30 | 0% |
1.4 | Support Board Module | Mar 25 | Apr 30 | |
1.4.1 | Equipments Supply | Mar 25 | Mar 27 | 100% |
1.4.2 | Construction of Board | Mar 28 | Apr 4 | 0% |
1.4.3 | Programming the board | Apr 5 | Apr 21 | |
1.4.3.1 | Serial port listener | Apr 5 | Apr 14 | 0% |
1.4.3.2 | Parallel port listener | Apr 15 | Apr 21 | 0% |
1.4.4 | Testing and Finalizing | Apr 22 | Apr 30 | 0% |
1.5 | Integrating Modules | May 1 | May 21 | |
1.5.1 | Admin tool - Bluetooth integration | May 1 | May 7 | 0% |
1.5.2 | Bluetooth - Support board Integration | May 8 | May 14 | 0% |
1.5.3 | FPGA - Support board Integration | May 15 | May 21 | 0% |
1.6 | Testing | May 22 | Jun 2 | |
1.6.1 | Determining test specifications | May 22 | May 25 | 0% |
1.6.2 | Unit Testing | May 26 | May 28 | 0% |
1.6.3 | Integration testing | May 28 | May 30 | 0% |
1.6.4 | Exhaustive Testing | Jun 1 | Jun 2 | 0% |
1.7 | Product Deployment | Jun 2 | Jun 10 | |
1.7.1 | Preparing User Manuals | Jun 2 | Jun 7 | 0% |
1.7.2 | Finalizing the product installer | Jun 8 | Jun 10 | 0% |