Poster In Blue

Company: I2Tech
Start: February 26, 2007
Finish: June 10, 2007
Report Date: April 4, 2007

Gantt Chart

Week 10, 2007 Week 11, 2007 Week 12, 2007 Week 13, 2007 Week 14, 2007 Week 15, 2007 Week 16, 2007 Week 17, 2007 Week 18, 2007 Week 19, 2007 Week 20, 2007 Week 21, 2007 Week 22, 2007 Week 23, 2007 Week 24, 2007
26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10
,

Tasks

WBS Name Start Finish Complete
1 Implementation of PosterInBlue Feb 26 Jun 10
1.1 Bluetooth Module Feb 26 Apr 30
1.1.1 Connection and Device Discovery Feb 26 Mar 11 100%
1.1.2 Sending text file Mar 12 Mar 14 100%
1.1.3 Sending V-Card Mar 15 Mar 24 0%
1.1.4 Sending images Mar 20 Mar 31 100%
1.1.5 Testing Apr 1 Apr 21 0%
1.1.6 Finalizing Bluetooth module Apr 22 Apr 30 0%
1.2 FPGA Module Feb 26 Apr 30
1.2.1 Configuration format desicion Feb 26 Mar 11 80%
1.2.2 Hardware Design for configuration Mar 12 Apr 8
1.2.2.1 Multiple image display Mar 12 Mar 16 100%
1.2.2.2 Poster duration design Mar 17 Mar 23 60%
1.2.2.3 Designing AT Command Generator Mar 24 Apr 8 0%
1.2.3 Testing Apr 8 Apr 21 0%
1.2.4 Finalizing FPGA Module Apr 22 Apr 30 0%
1.3 Admin tool Module Mar 11 Apr 30
1.3.1 Conf File Preparation Mar 11 Mar 24 80%
1.3.2 Sending Conf file over Bluetooth Mar 25 Apr 7 0%
1.3.3 Testing Apr 8 Apr 21 0%
1.3.4 Finalizing Admin tool module Apr 22 Apr 30 0%
1.4 Support Board Module Mar 25 Apr 30
1.4.1 Equipments Supply Mar 25 Mar 27 100%
1.4.2 Construction of Board Mar 28 Apr 4 0%
1.4.3 Programming the board Apr 5 Apr 21
1.4.3.1 Serial port listener Apr 5 Apr 14 0%
1.4.3.2 Parallel port listener Apr 15 Apr 21 0%
1.4.4 Testing and Finalizing Apr 22 Apr 30 0%
1.5 Integrating Modules May 1 May 21
1.5.1 Admin tool - Bluetooth integration May 1 May 7 0%
1.5.2 Bluetooth - Support board Integration May 8 May 14 0%
1.5.3 FPGA - Support board Integration May 15 May 21 0%
1.6 Testing May 22 Jun 2
1.6.1 Determining test specifications May 22 May 25 0%
1.6.2 Unit Testing May 26 May 28 0%
1.6.3 Integration testing May 28 May 30 0%
1.6.4 Exhaustive Testing Jun 1 Jun 2 0%
1.7 Product Deployment Jun 2 Jun 10
1.7.1 Preparing User Manuals Jun 2 Jun 7 0%
1.7.2 Finalizing the product installer Jun 8 Jun 10 0%

Resources

Name Short name Type Group Email
Barış Work
Ela Work
Ferhat Work
Gonca Work
Metin Work metinkayali@gmail.com