ID | Task Name | Resource Name(s) | Percent Completed |
---|---|---|---|
Week 1 (19/02/2007 - 25/02/2007) | |||
1 | Design Review | Iste Team | 100% |
2 | Work Package Reviews - WP Leaders Assignment | Iste Team | 100% |
3 | Schedule Overview - Live Schedule Preparation | Iste Team | 100% |
4 | CVS Setup | Iste Team | 100% |
Week 2 (26/02/2007 - 04/03/2007) | |||
5 | DBLayer Implementation - Newsserver operations | Anil, Goncagul, Hilal | 50% |
6 | DBLayer Implementation - User operations | Anil, Ferhat | 50% |
7 | Design Review of Another Group | Iste Team | 100% |
8 | Web Page Preparation | Goncagul, Hilal | 100% |
Week 3 (05/03/2007 - 11/03/2007) | |||
9 | DBLayer Implementation - Newsserver operations | Anil, Goncagul, Hilal | 100% |
10 | DBLayer Implementation - User operations | Anil, Ferhat | 100% |
11 | DBLayer Implementation - Archiving operations | Anil | 100% |
12 | DBLayer Implementation - Private Messaging & Chatting | Anil, Ferhat | 100% |
13 | Configuration Management Plan Preparation | Iste Team | 100% |
Week 4 (12/03/2007 - 18/03/2007) | |||
14 | DBLayer Implementation - Log Operation | Anil | 100% |
15 | DBLayer Implementation - Completion | Iste Team | 100% |
16 | WSLayer Implementation - WSDL & WSDD Creation | Anil | 100% |
17 | WSLayer Implementation - Deployment of the Web Services | Anil | 100% |
18 | Snapshot Demo Preparation | Iste Team | 100% |
Week 5 (19/03/2007 - 25/03/2007) | |||
19 | Mail Generator Implementation | Hilal | 100% |
20 | RSS Feed Generator Implementation | Goncagul | 100% |
21 | Atom Feed Generator Implementation | Goncagul | 100% |
22 | Work Package 1 - Revision | Iste Team | 60% |
23 | NewsAgent Core Testing | Anil, Hilal | 90% |
24 | NNTP Module Implementation - Connection Handling & Authentication | Anil, Goncagul | 100% |
25 | WEB Module GUI Implementation - Initial GUI Design | Ferhat, Hilal | 100% |
26 | User Account Operations Implementation - Home Page Classes | Anil, Ferhat | 100% |
27 | WEB Module GUI Implementation - Home Page Design | Ferhat, Goncagul, Hilal | 100% |
Week 6 (26/03/2007 - 01/04/2007) | |||
28 | NNTP Module Implementation - NNTP Command Handlers | Anil, Ferhat, Hilal | 100% |
29 | User Account Operations Implementation - Sign-in Page Classes | Anil, Ferhat | 100% |
30 | User Account Operations Implementation - Sign-up Page Classes | Anil, Ferhat | 100% |
31 | WEB Module GUI Implementation - Sign-in Page Design | Ferhat, Goncagul | 100% |
32 | WEB Module GUI Implementation - Sign-up Page Design | Ferhat, Hilal | 100% |
33 | E-mail Module Implementation-Mail Parser | Anil, Hilal | 0% |
34 | Atom Module Implementation-Atom Entry Handler | Anil, Goncagul | 50% |
35 | Work Package 1 - Revision | Iste Team | 70% |
Week 7 (02/04/2007 - 08/04/2007) | |||
36 | NNTP Module Implementation - SSL/TLS Implementation | Anil | 100% |
37 | User Account Operations Implementation - Account Operations Page Classes | Anil, Ferhat | 90% |
38 | News Server Operations Implementation - Article Operations Page Classes | Anil, Ferhat | 80% |
39 | WEB Module GUI Implementation - Account Information Page Design | Ferhat, Goncagul | 90% |
40 | WEB Module GUI Implementation - Article Operations Page Design | Ferhat, Hilal | 90% |
41 | E-mail Module Implementation - Authentication Manager | Hilal | 0% |
42 | E-mail Module Implementation - Mail Confirmation Manager | Hilal | 0% |
43 | Atom Module Implementation - Atom Entry Parser | Goncagul | 80% |
44 | Atom Module Implementation - Authentication Control | Anil, Goncagul | 100% |
Week 8 (09/04/2007 - 15/04/2007) | |||
45 | NNTP Module Implementation - Integration | Anil, Ferhat | 100% |
46 | NNTP Module Testing | Goncagul, Hilal | 90% |
47 | User Account Operations Implementation - Account Operations Page Classes | Anil, Ferhat | 100% |
48 | News Server Operations Implementation - Article Operations Page Classes | Anil, Ferhat | 100% |
49 | WEB Module GUI Implementation - Account Information Page Design | Ferhat, Goncagul | 100% |
50 | WEB Module GUI Implementation - Article Operations Page Design | Ferhat, Hilal | 100% |
51 | E-mail Module Implementation - Mail Submission Manager | Hilal | 100% |
52 | Atom Module Implementation - Feed Handler | Goncagul | 90% |
53 | Work Package 1 - Revision | Iste Team | 80% |
Week 9 (16/04/2007 - 22/04/2007) | |||
54 | News Server Operations Implementation - Newsgroups Operations Page Classes | Anil, Ferhat | 60% |
55 | WEB Module GUI Implementation - Newsgroups Operations Page Design | Ferhat | 80% |
56 | E-mail Module Implementation - Integration | Anil, Hilal | 90% |
57 | Atom Module Implementation - Integration | Anil, Goncagul | 90% |
58 | Integration Testing of the System | Goncagul, Hilal | 50% |
Week 10 (23/04/2007 - 29/04/2007) | |||
59 | E-mail Module Testing | Ferhat, Hilal | 80% |
60 | Atom Module Testing | Anil, Goncagul | 80% |
61 | Integration Testing of the System | Anil, Ferhat, Goncagul | 60% |
62 | News Server Operations Implementation - Newsgroups Operations Page Classes | Anil, Ferhat | 100% |
63 | WEB Module GUI Implementation - Newsgroups Operations Page Design | Ferhat, Goncagul, Hilal | 100% |
64 | Work Package 1 - Revision | Iste Team | 90% |
65 | First Release Package Preparation | Iste Team | 70% |
Week 11 (30/04/2007 - 06/05/2007) | |||
66 | Private Messaging and Chatting Operations Implementation - Private Messaging Operations Page Classes | Anil, Ferhat | 90% |
67 | Private Messaging and Chatting Operations Implementation - Chat Operations Page Classes | Goncagul, Hilal | 80% |
68 | Private Messaging and Chatting Operations Implementation - Chatting Handlers | Iste Team | 40% |
69 | Private Messaging and Chatting Operations Implementation - Synchronization Handlers | Iste Team | 20% |
70 | WEB Module GUI Implementation - Private Messaging Page Design | Ferhat, Hilal | 30% |
71 | WEB Module GUI Implementation - Chat Pop-up Page Design | Goncagul, Hilal | 20% |
72 | First Release Package Completion | Iste Team | 100% |
73 | Test Specification Report Preparation | Iste Team | 100% |
Week 12 (07/05/2007 - 13/05/2007) | |||
74 | Private Messaging and Chatting Operations Implementation - Private Messaging Operations Page Classes | Anil, Ferhat | 100% |
75 | Private Messaging and Chatting Operations Implementation - Chat Operations Page Classes | Goncagul, Hilal | 100% |
76 | Private Messaging and Chatting Operations Implementation - Chatting Handlers | Iste Team | 80% |
77 | Private Messaging and Chatting Operations Implementation - Synchronization Handlers | Iste Team | 80% |
78 | WEB Module GUI Implementation - Private Messaging Page Design | Ferhat, Hilal | 100% |
79 | WEB Module GUI Implementation - Chat Pop-up Page Design | Goncagul, Hilal | 100% |
Week 13 (14/05/2007 - 20/05/2007) | |||
80 | Web Module Implementation - Integration | Iste Team | 80% |
81 | Web Module Testing | Anil, Ferhat, Hilal | 80% |
82 | Security Testing | Anil, Goncagul | 30% |
83 | Performance Testing | Ferhat, Goncagul, Hilal | 20% |
84 | Work Package 1 - Revision | Iste Team | 100% |
85 | Presentation Preparation | Iste Team | 100% |
Week 14 (21/05/2007 - 27/05/2007) | |||
86 | Security Testing | Anil, Ferhat, Hilal | 90% |
87 | Performance Testing | Iste Team | 60% |
88 | Stress Testing | Ferhat, Goncagul, Hilal | 10% |
89 | Final Package Preparation | Iste Team | 20% |
Week 15 (28/05/2007 - 03/06/2007) | |||
90 | Performance Testing | Iste Team | 90% |
91 | Stress Testing | Iste Team | 70% |
92 | Final Package Preparation | Iste Team | 20% |
93 | Final Demo Preparation | Iste Team | 10% |
Week 16 (04/06/2007 - 11/06/2007) | |||
94 | Final Package Completion | Iste Team | 0% |
95 | Final Demo Completion | Iste Team | 0% |
96 | Final Demo | Iste Team | 0% |
97 | Competition | Iste Team | 0% |