| ID | Task Name | Resource Name(s) | Percent Completed |
|---|---|---|---|
| Week 1 (19/02/2007 - 25/02/2007) | |||
| 1 | Design Review | Iste Team | 100% |
| 2 | Work Package Reviews - WP Leaders Assignment | Iste Team | 100% |
| 3 | Schedule Overview - Live Schedule Preparation | Iste Team | 100% |
| 4 | CVS Setup | Iste Team | 100% |
| Week 2 (26/02/2007 - 04/03/2007) | |||
| 5 | DBLayer Implementation - Newsserver operations | Anil, Goncagul, Hilal | 50% |
| 6 | DBLayer Implementation - User operations | Anil, Ferhat | 50% |
| 7 | Design Review of Another Group | Iste Team | 100% |
| 8 | Web Page Preparation | Goncagul, Hilal | 100% |
| Week 3 (05/03/2007 - 11/03/2007) | |||
| 9 | DBLayer Implementation - Newsserver operations | Anil, Goncagul, Hilal | 100% |
| 10 | DBLayer Implementation - User operations | Anil, Ferhat | 100% |
| 11 | DBLayer Implementation - Archiving operations | Anil | 100% |
| 12 | DBLayer Implementation - Private Messaging & Chatting | Anil, Ferhat | 100% |
| 13 | Configuration Management Plan Preparation | Iste Team | 100% |
| Week 4 (12/03/2007 - 18/03/2007) | |||
| 14 | DBLayer Implementation - Log Operation | Anil | 100% |
| 15 | DBLayer Implementation - Completion | Iste Team | 100% |
| 16 | WSLayer Implementation - WSDL & WSDD Creation | Anil | 100% |
| 17 | WSLayer Implementation - Deployment of the Web Services | Anil | 100% |
| 18 | Snapshot Demo Preparation | Iste Team | 100% |
| Week 5 (19/03/2007 - 25/03/2007) | |||
| 19 | Mail Generator Implementation | Hilal | 100% |
| 20 | RSS Feed Generator Implementation | Goncagul | 100% |
| 21 | Atom Feed Generator Implementation | Goncagul | 100% |
| 22 | Work Package 1 - Revision | Iste Team | 60% |
| 23 | NewsAgent Core Testing | Anil, Hilal | 90% |
| 24 | NNTP Module Implementation - Connection Handling & Authentication | Anil, Goncagul | 100% |
| 25 | WEB Module GUI Implementation - Initial GUI Design | Ferhat, Hilal | 100% |
| 26 | User Account Operations Implementation - Home Page Classes | Anil, Ferhat | 100% |
| 27 | WEB Module GUI Implementation - Home Page Design | Ferhat, Goncagul, Hilal | 100% |
| Week 6 (26/03/2007 - 01/04/2007) | |||
| 28 | NNTP Module Implementation - NNTP Command Handlers | Anil, Ferhat, Hilal | 100% |
| 29 | User Account Operations Implementation - Sign-in Page Classes | Anil, Ferhat | 100% |
| 30 | User Account Operations Implementation - Sign-up Page Classes | Anil, Ferhat | 100% |
| 31 | WEB Module GUI Implementation - Sign-in Page Design | Ferhat, Goncagul | 100% |
| 32 | WEB Module GUI Implementation - Sign-up Page Design | Ferhat, Hilal | 100% |
| 33 | E-mail Module Implementation-Mail Parser | Anil, Hilal | 0% |
| 34 | Atom Module Implementation-Atom Entry Handler | Anil, Goncagul | 50% |
| 35 | Work Package 1 - Revision | Iste Team | 70% |
| Week 7 (02/04/2007 - 08/04/2007) | |||
| 36 | NNTP Module Implementation - SSL/TLS Implementation | Anil | 100% |
| 37 | User Account Operations Implementation - Account Operations Page Classes | Anil, Ferhat | 90% |
| 38 | News Server Operations Implementation - Article Operations Page Classes | Anil, Ferhat | 80% |
| 39 | WEB Module GUI Implementation - Account Information Page Design | Ferhat, Goncagul | 90% |
| 40 | WEB Module GUI Implementation - Article Operations Page Design | Ferhat, Hilal | 90% |
| 41 | E-mail Module Implementation - Authentication Manager | Hilal | 0% |
| 42 | E-mail Module Implementation - Mail Confirmation Manager | Hilal | 0% |
| 43 | Atom Module Implementation - Atom Entry Parser | Goncagul | 80% |
| 44 | Atom Module Implementation - Authentication Control | Anil, Goncagul | 100% |
| Week 8 (09/04/2007 - 15/04/2007) | |||
| 45 | NNTP Module Implementation - Integration | Anil, Ferhat | 100% |
| 46 | NNTP Module Testing | Goncagul, Hilal | 90% |
| 47 | User Account Operations Implementation - Account Operations Page Classes | Anil, Ferhat | 100% |
| 48 | News Server Operations Implementation - Article Operations Page Classes | Anil, Ferhat | 100% |
| 49 | WEB Module GUI Implementation - Account Information Page Design | Ferhat, Goncagul | 100% |
| 50 | WEB Module GUI Implementation - Article Operations Page Design | Ferhat, Hilal | 100% |
| 51 | E-mail Module Implementation - Mail Submission Manager | Hilal | 100% |
| 52 | Atom Module Implementation - Feed Handler | Goncagul | 90% |
| 53 | Work Package 1 - Revision | Iste Team | 80% |
| Week 9 (16/04/2007 - 22/04/2007) | |||
| 54 | News Server Operations Implementation - Newsgroups Operations Page Classes | Anil, Ferhat | 60% |
| 55 | WEB Module GUI Implementation - Newsgroups Operations Page Design | Ferhat | 80% |
| 56 | E-mail Module Implementation - Integration | Anil, Hilal | 90% |
| 57 | Atom Module Implementation - Integration | Anil, Goncagul | 90% |
| 58 | Integration Testing of the System | Goncagul, Hilal | 50% |
| Week 10 (23/04/2007 - 29/04/2007) | |||
| 59 | E-mail Module Testing | Ferhat, Hilal | 80% |
| 60 | Atom Module Testing | Anil, Goncagul | 80% |
| 61 | Integration Testing of the System | Anil, Ferhat, Goncagul | 60% |
| 62 | News Server Operations Implementation - Newsgroups Operations Page Classes | Anil, Ferhat | 100% |
| 63 | WEB Module GUI Implementation - Newsgroups Operations Page Design | Ferhat, Goncagul, Hilal | 100% |
| 64 | Work Package 1 - Revision | Iste Team | 90% |
| 65 | First Release Package Preparation | Iste Team | 70% |
| Week 11 (30/04/2007 - 06/05/2007) | |||
| 66 | Private Messaging and Chatting Operations Implementation - Private Messaging Operations Page Classes | Anil, Ferhat | 90% |
| 67 | Private Messaging and Chatting Operations Implementation - Chat Operations Page Classes | Goncagul, Hilal | 80% |
| 68 | Private Messaging and Chatting Operations Implementation - Chatting Handlers | Iste Team | 40% |
| 69 | Private Messaging and Chatting Operations Implementation - Synchronization Handlers | Iste Team | 20% |
| 70 | WEB Module GUI Implementation - Private Messaging Page Design | Ferhat, Hilal | 30% |
| 71 | WEB Module GUI Implementation - Chat Pop-up Page Design | Goncagul, Hilal | 20% |
| 72 | First Release Package Completion | Iste Team | 100% |
| 73 | Test Specification Report Preparation | Iste Team | 100% |
| Week 12 (07/05/2007 - 13/05/2007) | |||
| 74 | Private Messaging and Chatting Operations Implementation - Private Messaging Operations Page Classes | Anil, Ferhat | 100% |
| 75 | Private Messaging and Chatting Operations Implementation - Chat Operations Page Classes | Goncagul, Hilal | 100% |
| 76 | Private Messaging and Chatting Operations Implementation - Chatting Handlers | Iste Team | 80% |
| 77 | Private Messaging and Chatting Operations Implementation - Synchronization Handlers | Iste Team | 80% |
| 78 | WEB Module GUI Implementation - Private Messaging Page Design | Ferhat, Hilal | 100% |
| 79 | WEB Module GUI Implementation - Chat Pop-up Page Design | Goncagul, Hilal | 100% |
| Week 13 (14/05/2007 - 20/05/2007) | |||
| 80 | Web Module Implementation - Integration | Iste Team | 80% |
| 81 | Web Module Testing | Anil, Ferhat, Hilal | 80% |
| 82 | Security Testing | Anil, Goncagul | 30% |
| 83 | Performance Testing | Ferhat, Goncagul, Hilal | 20% |
| 84 | Work Package 1 - Revision | Iste Team | 100% |
| 85 | Presentation Preparation | Iste Team | 100% |
| Week 14 (21/05/2007 - 27/05/2007) | |||
| 86 | Security Testing | Anil, Ferhat, Hilal | 90% |
| 87 | Performance Testing | Iste Team | 60% |
| 88 | Stress Testing | Ferhat, Goncagul, Hilal | 10% |
| 89 | Final Package Preparation | Iste Team | 20% |
| Week 15 (28/05/2007 - 03/06/2007) | |||
| 90 | Performance Testing | Iste Team | 90% |
| 91 | Stress Testing | Iste Team | 70% |
| 92 | Final Package Preparation | Iste Team | 20% |
| 93 | Final Demo Preparation | Iste Team | 10% |
| Week 16 (04/06/2007 - 11/06/2007) | |||
| 94 | Final Package Completion | Iste Team | 0% |
| 95 | Final Demo Completion | Iste Team | 0% |
| 96 | Final Demo | Iste Team | 0% |
| 97 | Competition | Iste Team | 0% |