| TASK NAME | DURATION | START DATE | END DATE | ASSIGNED | DONE |
| WP0. Project Management | |||||
| Living Schedule | 3 days | 23.02.2007 | 25.02.2007 | All | 100% |
| Project web page | 14 days | 26.02.2007 | 11.03.2007 | Fırat | 100% |
| Configuration management plan | 8 days | 04.03.2007 | 11.03.2007 | all | 100% |
| WP1. Prototype and Design Review | |||||
| Mailing list requirements review | 9 days | 25.02.2007 | 05.03.2007 | Yunus | 100% |
| Security module re-design | 19 days | 25.02.2007 | 15.03.2007 | Yusuf,Dilek | 100% |
| Ensuring performance | 9 days | 25.02.2007 | 05.03.2007 | Fırat | 100% |
| Forum GUI enhancement | 24 days | 25.02.2007 | 20.03.2007 | Eda | 80% |
| WP2. SMTP2NNTP Module Development | |||||
| SMTP2NNTP article format conversion | 13 days | 06.03.2007 | 18.03.2007 | Yusuf | 100% |
| Spam filtering feature | 15 days | 20.03.2007 | 03.04.2007 | Yusuf,Eda | 100% |
| Virus Filtering Feature | 7 days | 21.03.2007 | 28.03.2007 | Dilek | 100% |
| Unit testing | 3 days | 04.04.2007 | 07.04.2007 | Yusuf,Eda | 100% |
| SMTP2NNTP and NNTP2SMTP integration | 3 days | 08.04.2007 | 10.04.2007 | Yusuf,Eda | 100% |
| Performance testing | 3 days | 10.04.2007 | 12.04.2007 | Yusuf | 100% |
| Security testing | 3 days | 13.04.2007 | 15.04.2007 | Yusuf,Eda | 100% |
| Globalization testing | 2 days | 16.04.2007 | 17.04.2007 | Eda | 0% |
| First release | 0 day | 18.04.2007 | 18.04.2007 | Yusuf,Eda | 100% |
| Beta testing | 5 days | 19.04.2007 | 23.04.2007 | Yusuf,Eda | 100% |
| Improvements | 12 days | 19.04.2007 | 30.04.2007 | Yusuf,Eda | 100% |
| Final release | 0 day | 01.05.2007 | 01.05.2007 | Yusuf,Eda | 100% |
| WP3. User Authentication Module Implementation | |||||
| Login module implementation | 15 days | 07.03.2007 | 21.03.2007 | Fırat | 100% |
| SSL certification implementation | 25 days | 07.03.2007 | 31.03.2007 | Yunus | 60% |
| User delegation implementation | 26 days | 22.03.2007 | 16.04.2007 | Fırat | 100% |
| Database security configuration | 16 days | 01.04.2007 | 16.04.2007 | Yunus | 100% |
| Alpha testing | 6 days | 17.04.2007 | 22.04.2007 | Yunus,Fırat | 80% |
| First Release | 0 day | 23.04.2007 | 23.04.2007 | Yunus,Fırat | 100% |
| Beta testing and debugging | 8 days | 24.04.2007 | 01.05.2007 | Yunus,Fırat | 80% |
| Improvements | 8 days | 24.04.2007 | 01.05.2007 | Yunus,Fırat | 100% |
| Final release | 0 day | 01.05.2007 | 01.05.2007 | Yunus,Fırat | 100% |
| WP4. Admin Module Implementation | |||||
| Admin GUI implementation | 2 days | 06.03.2007 | 15.03.2007 | Dilek | 80% |
| Server configuration implementation | 2 days | 16.03.2007 | 23.03.2007 | Dilek, Yunus | 70% |
| Newsgroup and mailing list conf. İmplementation | 8 days | 24.03.2007 | 01.04.2007 | Dilek | 20% |
| User management implementation | 6 days | 10.04.2007 | 15.04.2007 | Dilek | 90% |
| Logging implementation | 5 days | 16.04.2007 | 20.04.2007 | Dilek, Fırat | 70% |
| Alpha testing | 2 days | 21.04.2007 | 24.04.2007 | Dilek | 70% |
| First Release | 0 day | 25.04.2007 | 25.04.2007 | Dilek | 70% |
| Beta testing and debugging | 3 days | 26.04.2007 | 30.04.2007 | Dilek | 70% |
| Improvements | 3 days | 26.04.2007 | 30.04.2007 | Dilek | 70% |
| Final release | 0 day | 01.05.2007 | 01.05.2007 | Dilek | 70% |
| WP5: Finalizing Package | |||||
| Integrating Modules | 2 days | 02.05.2007 | 03.05.2007 | All | 70% |
| First Release Alpha Testing | 2 days | 04.05.2007 | 05.05.2007 | All | 70% |
| First Release Beta Testing & Debugging | 2 days | 04.05.2007 | 05.05.2007 | All | 70% |
| First Release | 0 day | 06.05.2007 | 06.05.2007 | All | 70% |
| Improvements | 30 days | 08.05.2007 | 08.06.2007 | All | 70% |
| Final Release Alpha Testing | 4 days | 09.06.2007 | 12.06.2007 | All | 70% |
| Final Release Beta Testing & Debugging | 4 days | 13.06.2007 | 16.06.2007 | All | 70% |
| Final Release | 0 day | 17.06.2007 | 17.06.2007 | All | 70% |