LIVING SCHEDULE

 

TASK NAME DURATION START DATE END DATE ASSIGNED DONE
WP0. Project Management
Living Schedule 3 days 23.02.2007 25.02.2007 All 100%
Project web page 14 days 26.02.2007 11.03.2007 Fırat 100%
Configuration management plan 8 days 04.03.2007 11.03.2007 all 100%
WP1. Prototype and Design Review
Mailing list requirements review 9 days 25.02.2007 05.03.2007 Yunus 100%
Security module re-design 19 days 25.02.2007 15.03.2007 Yusuf,Dilek 100%
Ensuring performance 9 days 25.02.2007 05.03.2007 Fırat 100%
Forum GUI enhancement 24 days 25.02.2007 20.03.2007 Eda 80%
WP2. SMTP2NNTP Module Development
SMTP2NNTP article format conversion 13 days 06.03.2007 18.03.2007 Yusuf 100%
Spam filtering feature 15 days 20.03.2007 03.04.2007 Yusuf,Eda 100%
Virus Filtering Feature 7 days 21.03.2007 28.03.2007 Dilek 100%
Unit testing 3 days 04.04.2007 07.04.2007 Yusuf,Eda 100%
SMTP2NNTP and NNTP2SMTP integration 3 days 08.04.2007 10.04.2007 Yusuf,Eda 100%
Performance testing 3 days 10.04.2007 12.04.2007 Yusuf 100%
Security testing 3 days 13.04.2007 15.04.2007 Yusuf,Eda 100%
Globalization testing 2 days 16.04.2007 17.04.2007 Eda 0%
First release 0 day 18.04.2007 18.04.2007 Yusuf,Eda 100%
Beta testing 5 days 19.04.2007 23.04.2007 Yusuf,Eda 100%
Improvements 12 days 19.04.2007 30.04.2007 Yusuf,Eda 100%
Final release 0 day 01.05.2007 01.05.2007 Yusuf,Eda 100%
WP3. User Authentication Module Implementation
Login module implementation 15 days 07.03.2007 21.03.2007 Fırat 100%
SSL certification implementation 25 days 07.03.2007 31.03.2007 Yunus 60%
User delegation implementation 26 days 22.03.2007 16.04.2007 Fırat 100%
Database security configuration 16 days 01.04.2007 16.04.2007 Yunus 100%
Alpha testing 6 days 17.04.2007 22.04.2007 Yunus,Fırat 80%
First Release 0 day 23.04.2007 23.04.2007 Yunus,Fırat 100%
Beta testing and debugging 8 days 24.04.2007 01.05.2007 Yunus,Fırat 80%
Improvements 8 days 24.04.2007 01.05.2007 Yunus,Fırat 100%
Final release 0 day 01.05.2007 01.05.2007 Yunus,Fırat 100%
WP4. Admin Module Implementation
Admin GUI implementation 2 days 06.03.2007 15.03.2007 Dilek 80%
Server configuration implementation 2 days 16.03.2007 23.03.2007 Dilek, Yunus 70%
Newsgroup and mailing list conf. İmplementation 8 days 24.03.2007 01.04.2007 Dilek 20%
User management implementation 6 days 10.04.2007 15.04.2007 Dilek 90%
Logging implementation 5 days 16.04.2007 20.04.2007 Dilek, Fırat 70%
Alpha testing 2 days 21.04.2007 24.04.2007 Dilek 70%
First Release 0 day 25.04.2007 25.04.2007 Dilek 70%
Beta testing and debugging 3 days 26.04.2007 30.04.2007 Dilek 70%
Improvements 3 days 26.04.2007 30.04.2007 Dilek 70%
Final release 0 day 01.05.2007 01.05.2007 Dilek 70%
WP5: Finalizing Package  
Integrating Modules 2 days 02.05.2007 03.05.2007 All 70%
First Release Alpha Testing 2 days 04.05.2007 05.05.2007 All 70%
First Release Beta Testing & Debugging 2 days 04.05.2007 05.05.2007 All 70%
First Release 0 day 06.05.2007 06.05.2007 All 70%
Improvements 30 days 08.05.2007 08.06.2007 All 70%
Final Release Alpha Testing 4 days 09.06.2007 12.06.2007 All 70%
Final Release Beta Testing & Debugging 4 days 13.06.2007 16.06.2007 All 70%
Final Release 0 day 17.06.2007 17.06.2007 All 70%

 