Living Schedule

25/02/2007

Task Start Finish Duration Assigned To Status
Design review 26.02 02.03 4 days All Members 100%
Web Page preparation 04.03 11.03 8 days All Members 100%
CM planning 08.03 11.03 3 days All Members 100%
Coding 05.03 7.05 63 days All Members 0%
Review / First dev. snapshots 05.03 09.03 5 days All Members 0%
Database development 05.03 14.03 10 days Hüsna Işık 0%
SMTP configuration 15.03 27.03 13 days Fatma Özyıldırım 0%
Creating subscription module 23.03 27.03 5 days Ainura Madylova 0%
HTTP- SMTP Integration / DEMO 28.03 12.04 16 days Asiye Kıyak 0%
NNTP-SMTP Integration / DEMO 28.03 12.04 16 days Esin Yöndem 0%
Web Page (GUI) development 05.04 20.04 16 days Ainura Madylova- Asiye Kıyak 0%
NNTP-SMTP-HTTP Integration / DEMO 21.04 28.04 8 days Hüsna Işık- Esin Yöndem 0%
RSS Configuration- Update 29.04 02.05 3 days Fatma Özyıldırım 0%
Scenario Creation 03.05 07.05 5 days All Members 0%
Testing 07.05 31.05 25 days All Members 0%
Unit Test 1/ NNTP-SMTP 07.05 13.05 7 days Ainura Madylova 0%
Unit Test 2/ HTTP-SMTP-RSS 14.05 20.05 7 days Asiye Kıyak - Fatma Özyıldırım 0%
Unit Test 3/ NNTP-HTTP-RSS 21.05 27.05 7 days Esin Yöndem - Hüsna Işık 0%
Integration Testing 28.05 31.05 4 days All Members 0%
Documentation 01.06 10.06 10 days All Members 0%
Installation Guide preparation 01.06 10.06 10 days Fatma Özyıldırım 0%
User Manual Preparation 01.06 10.06 10 days Ainura Madylova - Esin Yöndem 0%
Help Documentation Preparation 01.06 10.06 10 days Hüsna Işık - Asiye Kıyak 0%