Task | Start | Finish | Duration | Assigned To | Status |
Design review | 26.02 | 02.03 | 4 days | All Members | 100% |
Web Page preparation | 04.03 | 11.03 | 8 days | All Members | 100% |
CM planning | 08.03 | 11.03 | 3 days | All Members | 100% |
Coding | 05.03 | 7.05 | 63 days | All Members | 0% |
Review / First dev. snapshots | 05.03 | 09.03 | 5 days | All Members | 0% |
Database development | 05.03 | 14.03 | 10 days | Hüsna Işık | 0% |
SMTP configuration | 15.03 | 27.03 | 13 days | Fatma Özyıldırım | 0% |
Creating subscription module | 23.03 | 27.03 | 5 days | Ainura Madylova | 0% |
HTTP- SMTP Integration / DEMO | 28.03 | 12.04 | 16 days | Asiye Kıyak | 0% |
NNTP-SMTP Integration / DEMO | 28.03 | 12.04 | 16 days | Esin Yöndem | 0% |
Web Page (GUI) development | 05.04 | 20.04 | 16 days | Ainura Madylova- Asiye Kıyak | 0% |
NNTP-SMTP-HTTP Integration / DEMO | 21.04 | 28.04 | 8 days | Hüsna Işık- Esin Yöndem | 0% |
RSS Configuration- Update | 29.04 | 02.05 | 3 days | Fatma Özyıldırım | 0% |
Scenario Creation | 03.05 | 07.05 | 5 days | All Members | 0% |
Testing | 07.05 | 31.05 | 25 days | All Members | 0% |
Unit Test 1/ NNTP-SMTP | 07.05 | 13.05 | 7 days | Ainura Madylova | 0% |
Unit Test 2/ HTTP-SMTP-RSS | 14.05 | 20.05 | 7 days | Asiye Kıyak - Fatma Özyıldırım | 0% |
Unit Test 3/ NNTP-HTTP-RSS | 21.05 | 27.05 | 7 days | Esin Yöndem - Hüsna Işık | 0% |
Integration Testing | 28.05 | 31.05 | 4 days | All Members | 0% |
Documentation | 01.06 | 10.06 | 10 days | All Members | 0% |
Installation Guide preparation | 01.06 | 10.06 | 10 days | Fatma Özyıldırım | 0% |
User Manual Preparation | 01.06 | 10.06 | 10 days | Ainura Madylova - Esin Yöndem | 0% |
Help Documentation Preparation | 01.06 | 10.06 | 10 days | Hüsna Işık - Asiye Kıyak | 0% |