| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Management | 76 days | February 26 | June 11 | All | 20% |
| 1.1 | First Dev Snapshot Demo | 11 days | February 26 | March 12 | All | 50% |
| 1.2 | First Release | 42 days | March 2 | April 30 | All | 20% |
| 1.3 | Final Release | 33 days | April 26 | June 11 | All | 0% |
| 2 | Documentation | 76 days | February 26 | June 11 | All | 50% |
| 2.1 | Configuration Management Plan | 12 days | February 26 | March 13 | All | 100% |
| 2.2 | Coding Standards | 10 days | February 26 | March 10 | All | 100% |
| 2.3 | Test Specification Plan | 9 days | May 1 | May 11 | All | 0% |
| 2.4 | User Manual | 7 days | June 1 | June 11 | All | 0% |
| 3 | Administration | 15 days | February 26 | March 16 | 60% | |
| 3.1 | Setup CVS | 15 days | February 26 | March 16 | 60% | |
| 4 | Website | 58 days | March 1 | June 11 | All | 0% |
| 4.1 | Initial Content Setup | 3 days | March 1 | March 5 | All | 0% |
| 4.2 | Snapshot Screenshots | 9 days | March 6 | March 16 | All | 0% |
| 4.3 | First Release ScreenShots | 9 days | May 1 | May 11 | All | 0% |
| 4.4 | Final Release Screenshots | 7 days | June 1 | June11 | All | 0% |
| 5 | Network Engine Development | 66 days | February 26 | May 28 | Onur | 10% |
| 5.1 | Client Side Network Engine Dev. | 57 days | February 26 | May 15 | Onur | 10% |
| 5.2 | Server Side Network Engine Dev. | 66 days | February 26 | May 28 | Onur | 10% |
| 6 | Resource Production | 76 days | February 26 | June 11 | Fırat,Abdulkerim | 10% |
| 6.1 | Character Models | 35 days | February 26 | April 13 | Abdulkerim | 10% |
| 6.2 | Character Animations | 30 days | March 12 | April 20 | Abdulkerim | 5% |
| 6.3 | Models | 22 days | March 12 | April 10 | Abdulkerim | 20% |
| 6.4 | Texture | 38 days | March 8 | April 30 | Fırat,Abdulkerim | 40% |
| 6.5 | Map | 70 days | March 5 | June 11 | Abdulkerim | 10% |
| 7 | Graphics Engine Development | 76 days | March 1 | June 11 | All | 7% |
| 7.1 | Rendering | 73 days | March 1 | June 11 | All | 10% |
| 7.2 | Camera | 73 days | March 1 | June 11 | Özgür | 5% |
| 8 | Game Engine Development | 76 days | February 26 | June 11 | All | 0% |
| 8.1 | Client Side Game Engine Dev. | 76 days | February 26 | June 11 | All | 6% |
| 8.1.a | Input Handler | 35 days | February 26 | April 13 | Onur,Özgür | 30% |
| 8.1.b | Physics | 40 days | February 26 | April 20 | Onur,Özgür | 0% |
| 8.1.c | Interaction | 76 days | February 26 | June 11 | Fırat,Abdulkerim | 0% |
| 8.1.d | Event Handler | 76 days | February 26 | June 11 | Fırat,Abdulkerim | 0% |
| 8.2 | Server Side Game Engine Dev. | 76 days | February 26 | June 11 | All | 0% |
| 9 | GUI Development | 76 days | February 26 | June 11 | All | 0% |
| 9.1 | Game Main Menu GUI | 30 days | March 12 | April 20 | Mehmet,Onur | 0% |
| 9.2 | Options Menu GUI | 30 days | March 12 | April 20 | Mehmet,Onur | 0% |
| 9.3 | Team Management Menu GUI | 36 days | March 12 | April 30 | Mehmet,Onur | 0% |
| 9.4 | In Game Menu GUI | 66 days | March 12 | June 11 | Mehmet,Fırat | 0% |
| 9.5 | Chat GUI | 15 days | February 26 | March 12 | Onur | 15% |
| 9.6 | Game Pause Menu GUI | 15 days | April 2 | April 20 | Mehmet,Fırat | 0% |
| 9.7 | Help Menu GUI | 20 days | May 15 | June 11 | Abdulkerim,Mehmet,Onur | 0% |
| 9.8 | GUI-Game interaction development | 76 days | February 26 | June 11 | All | 0% |
| 10 | Testing | 30 days | May 1 | June 11 | Fırat,Özgür,Mehmet | 0% |
| 10.1 | Alpha Testing | 11 days | May 1 | May 15 | Fırat,Özgür,Mehmet | 0% |
| 10.2 | Beta Testing | 13 days | May 21 | June 6 | Fırat,Özgür,Mehmet | 0% |
| 10.3 | Debugging | 20 days | May 15 | June 11 | Fırat,Özgür,Mehmet | 0% |
| 11 | Game Data | 73 days | March 1 | June 11 | All | 0% |
| 12 | AI | 30 days | May 1 | June 6 | Fırat,Mehmet | 0% |
| 13 | Level Puzzles Implementation | 33 days | April 17 | May 30 | Özgür,Fırat | 0% |
| 14 | Puzzle Database Building | 33 days | April 17 | May 30 | Özgür,Fırat | 0% |
| 15 | Music | 57 days | February 26 | May 13 | Fırat | 5% |
| 15 | Sound | 57 days | February 26 | May 13 | Fırat | 5% |
| 17 | Chat Module Development | 15 days | February 26 | March 12 | Onur | 20% |