TASK DESCRIPTION
DURATION
START
FINISH
COMPLETE
ASSIGNED TO
GUI MODULE
80 days
25.02.08
15.05.08
%75
All

BasicToolbar Class Implementation

30 days
24.03.08
24.04.08
%80
Serap

EnhancementToolbar Class Implementation

30 days
24.03.08
24.04.08
%50
Meryem

ProjectManager Class Implementation

40 days
14.03.08
24.04.08
%85
Hanife

MainWindow Class Implementation

60 days
25.02.08
26.04.08
%90
All

Testing & Optimization of Module

30 days
15.04.08
15.05.08
%75
Serra, Meryem
FILE SYSTEM MODULE
 

FileSystemHandler Class Implementation

40 days
10.03.08
20.04.08
%75
Serra

ImageData Class Implementation

5 days
01.03.08
06.03.08
%100
Hanife

Testing & Optimization of Module

20 days
05.04.08
25.04.08
%75
Serap, Hanife
PHOTOGRAMMETRY MODULE
 

PhotogrammetryManagerToolbar Class Implementation

5 days
25.03.08
30.03.08
%100
Serra

PhotogrammetryManager Class Implementation

80 days
25.02.08
15.05.08
%50
All

Testing & Optimization of Module

5 days
15.05.08
20.05.08
Meryem
MOSAIC SUBMODULE
 

Method Searching

3 days
03.12.07
06.12.07
%100
All

Mosaic Class Implementation

115 days
06.01.08
01.05.08
%75
All

Testing and Optimization

10 days
02.05.08
12.05.08
Serra
DEM SUBMODULE
 

Method Searching

20 days
05.04.08
25.04.08
%60
Serra, Meryem

DEM Class Implementation

22 days
08.04.08
30.04.08
%40
All

Testing and Optimization

5 days
30.04.08
05.05.08
Hanife, Serap
ORTHOPHOTO SUBMODULE
 

Method Searching

5 days
25.04.08
30.04.08
Hanife, Serap

Orthophoto Class Implementation

20 days
30.04.08
20.05.08
All

Testing and Optimization

5 days
20.05.08
25.05.08
Serra, Meryem
WHOLE SYSTEM TEST & OPTIMIZATION
15 days
25.05.08
10.06.08
All
OTHER
 

Configuration Management Plan

5 days
04.03.08
09.03.08
Meryem

Web site

105 days
25.02.08
10.06.08
Hanife