Final Package

Jun. 15, 2008

Final package is ready. The kernel files of AP400 and the pic ...

User Manual

Jun. 15, 2008

User manual is ready. This manual decribes how to build ...

First Snapshot

Mar. 23, 2008

First snapshot is ready. This is a video about our PCB ...

Gantt Chart

Feb. 26, 2008

Living schedule part is ready. Gantt Chart for the second term ...

Weekly Reports

Jan. 20, 2008

Weekly reports are updated. Weekly reports about the project work progress ...

Final Design Report

Jan. 18, 2008

Final Design Report is the detailed version of initial design report ...

Presentation

Jan. 4, 2008

Presentation describes our project ...

Initial Design Report

Dec. 7, 2007

Initial Design Report includes the hardware and software design ...

Requirement Analysis Report

Nov. 3, 2007

Requirement Analysis Report is ready. The analysis of the requirements of the ...

Proposal Report

Oct. 8, 2007

Proposal Report is ready. The introduction of the the project and Güçlü Kadro ...

Güçlü Kadro Software

Oct. 1, 2007

Güçlü Kadro project description is ready. Wireless communications are rapidly growing ...

CENG Senior Project