Task
|
Duration
|
Start
|
Finish
|
Assigned To
|
Status
|
Design Review
|
6
days
|
27
February
|
4
March
|
All
Members
|
%100
Completed
|
Web page Preparation
|
4
days
|
2
March
|
5
March
|
Volkan&Ali
Caner
|
%100
Completed
|
Configuration Management Planning
|
7
days
|
5
March
|
11
March
|
All
Members
|
%100
Completed
|
Implementation
|
85
days
|
14
February
|
10
May
|
All
Members
|
%55
Completed
|
Database
Module Implementation
|
24 days
|
15 February
|
11 March
|
Okan
|
%80 Completed
|
Editor Module
Implementation
|
60 days
|
13 February
|
15 April
|
Volkan
|
%55 Completed
|
Panel Module
Implementation
|
55 days
|
14 February
|
10 April
|
Halil&Okan
|
%80 Completed
|
File Explorer Panel
|
12 days
|
15
February
|
27
February
|
Halil
|
%95
Completed
|
Ajax Action Panel
|
14 days
|
13 March
|
27 March
|
Okan
|
%20
Completed
|
Solution Explorer Panel
|
12 days
|
1 March
|
12 March
|
Halil
|
%95
Completed
|
ToolBox Panel
|
26 days
|
13 March
|
10 April
|
Halil
|
%75
Completed
|
Debugger
Module Implementation
|
30 days
|
10 April
|
10 May
|
Halil
|
%0 Completed
|
FTP Module
Implementation
|
30 days
|
15 February
|
15 March
|
Ali Caner
|
%85
Completed
|
CVS Module
Implementation
|
30 days
|
16 March
|
16 April
|
Ali Caner
|
%0 Completed
|
GUI Design
Implementation
|
60 days
|
13 February
|
15 April
|
Okan
|
%80 Completed
|
Integration
|
45 days
|
31 March
|
15 May
|
All Members
|
%50 Completed
|
Testing
|
18
days
|
15
May
|
2
June
|
All
Members
|
%0
Completed
|
Unit Testing
|
4 days
|
15 May
|
18 May
|
All Members
|
%0 Completed
|
Integration Testing
|
3 days
|
19 May
|
21 May
|
All Members
|
%0 Completed
|
Validation Testing
|
2 days
|
22 May
|
23 May
|
All Members
|
%0 Completed
|
Correction
|
7 days
|
24 May
|
1 June
|
All Members
|
%0 Completed
|
System
Validation
|
10 days
|
23 May
|
2 June
|
All Members
|
%0 Completed
|
Preparation
of User Manuals
|
10 days
|
26 May
|
5 June
|
All Members
|
%0 Completed
|