Information | Duration | Start | End | Assigned | Progress |
---|---|---|---|---|---|
RIS webpage design | 42 days | 10 March | 21 April | Caner | 100% |
Design of the registration page | 7 days | 10 March | 17 March | Caner | 100% |
Design of the machinist page | 7 days | 17 March | 24 March | Caner | 100% |
Design of the home pages | 7 days | 24 March | 31 March | Caner | 100% |
Design of the schedule page | 7 days | 1 april | 7 April | Caner | 100% |
Design of knowledge-db page | 14 days | 7 April | 21 April | Caner | 100% |
Optimum path searching | 35 days | 10 March | 14 April | Isil | 100% |
Implementing the algorithm | 15 days | 10 March | 25 March | Isil | 100% |
Filtering the results | 10 days | 25 March | 3 April | Isil | 100% |
Integration to the interface | 10 days | 4 April | 14 April | Isil | 100% |
Creating the map | 22 days | 7 March | 31 March | Cagri | 100% |
Deciding the station points | 5 days | 7 March | 12 March | Cagri | 100% |
Drawing the railways | 5 days | 12 March | 19 March | Cagri | 100% |
Map interaction implementations | 5 days | 19 March | 24 March | Cagri | 100% |
Marking coordinates on map | 7 days | 24 March | 31 March | Cagri | 100% |
Loading city coordinates to database | 8 days | 10 March | 8 April | Burkay-Cagri | 100% |
Preparing data | 4 days | 10 March | 25 March | Burkay-Cagri | 100% |
Loading data to database tables | 4 days | 25 March | 8 April | Burkay-Cagri | 100% |
Integration of search algorithm to new map | 5 days | 4 April | 14 April | Isil | 100% |
Schedule sub-module implementation | 5 days | 14 April | 19 April | Isil | 100% |
Knowledge database implementation | 16 days | 19 April | 5 May | Isil | 100% |
Sending a message to the system | 4 days | 19 April | 23 April | Isil | 100% |
Editing the message | 4 days | 23 April | 27 April | Isil | 100% |
Answering to that message | 4 days | 27 April | 1 May | Isil | 100% |
Escalation to other admins | 4 days | 1 May | 5 May | Isil | 100% |
Design of journey module | 5 days | 14 April | 19 April | Caner | 100% |
Implementation of news module | 7 days | 19 April | 23 April | Isil | 100% |
Design of news sub-module | 5 days | 23 April | 28 April | Caner | 100% |
Update sub-module | 6 days | 25 April | 1 May | Isil | 100% |
Design of update sub-module | 5 days | 1 May | 6 May | Caner | 100% |
Accelerometer | 5 days | 1 May | 6 May | Burkay-Cagri | 100% |
GPS Simulation | 20 days | 10 March | 30 March | Burkay | 98% |
Accelerometer Integration | 7 days | 10 May | 17 May | Burkay | 100% |
GPS Tracking on map | 10 Days | 25 May | 5 June | Cagri | 97% |