Project Start Date:
Wed 20.02.08
Project Finish Date:
Wed 04.06.08
Gantt Chart of the Schedule (pdf format)
Living Schedule
| ID | Name |
Duration | Start_Date | Finish | Resource_Names |
|---|---|---|---|---|---|
| 1 | Detailed Database Implementation |
2 days | Wed 20.02.08 | Fri 22.02.08 | |
| 2 | Defining Entity Relations |
1 day | Wed 20.02.08 | Thu 21.02.08 | Hanifi Ozturk |
| 3 | Creating New Tables |
1 day | Wed 20.02.08 | Thu 21.02.08 | Serkan Caglar |
| 4 | Testing the Database |
1 day | Thu 21.02.08 | Fri 22.02.08 | Serdar Kocbey |
| 5 | Developing HSBS Sentinel Software / Protocol |
29 days | Wed 20.02.08 | Thu 20.03.08 | |
| 6 | Designing PCB (SP07 (v2.0)) |
7 days | Wed 20.02.08 | Wed 27.02.08 | Burak Cansizoglu |
| 7 | Change the Protocol of Serial Data Reading to AP-400 Driven Mode |
10 days | Wed 20.02.08 | Sat 01.03.08 | Serdar Kocbey |
| 8 | Bringing Back the Wireless Communication |
10 days | Wed 20.02.08 | Sat 01.03.08 | Serkan Caglar |
| 9 | Adding AP-400 DHCP Client Property |
10 days | Wed 20.02.08 | Sat 01.03.08 | Burak Cansizoglu Serkan Caglar |
| 10 | Improving the Algorithm of RS-232 Protocol |
10 days | Sat 01.03.08 | Tue 11.03.08 | Hanifi Ozturk Serdar Kocbey |
| 11 | Improving the Algorithm of Server to Receive Data Sent from HSBS_Sentinel |
19 days | Sat 01.03.08 | Thu 20.03.08 | Serkan Caglar Serdar Kocbey |
| 12 | Implementing New Wireless Nodes |
7 days | Thu 20.03.08 | Thu 27.03.08 | |
| 13 | Assembling new SP07's (v2.0) |
4 days | Thu 20.03.08 | Mon 24.03.08 | Hanifi Ozturk |
| 14 | Implementing New SP07 Module |
4 days | Thu 20.03.08 | Mon 24.03.08 | Hanifi Ozturk |
| 15 | SP07 Component Testing |
1 day | Mon 24.03.08 | Tue 25.03.08 | Hanifi Ozturk |
| 16 | Assembling New HSBS Sentinels |
1 day | Mon 24.03.08 | Tue 25.03.08 | Serkan Caglar |
| 17 | Testing HSBS_Sentinels (v2.0) |
1 day | Tue 25.03.08 | Wed 26.03.08 | Serdar Kocbey |
| 18 | Building a Wireless Network and Testing |
1 day | Wed 26.03.08 | Thu 27.03.08 | Burak Cansizoglu |
| 19 | Implementing the GUI |
45 days | Tue 18.03.08 | Sat 03.05.08 | |
| 20 | Java / Swing Studies |
5 days | Tue 18.03.08 | Sun 23.03.08 | Serkan Caglar Serdar Kocbey Burak Cansizoglu Hanifi Ozturk |
| 21 | Implementing Node Monitor |
12 days | Sun 23.03.08 | Fri 04.04.08 | Serdar Kocbey Serkan Caglar Burak Cansizoglu |
| 22 | Implementing Data Analyzer |
14 days | Fri 04.04.08 | Fri 18.04.08 | Serkan Caglar Serdar Kocbey Burak Cansizoglu Hanifi Ozturk |
| 23 | Implementing Report Generator |
14 days | Fri 18.04.08 | Sat 03.05.08 | Serkan Caglar Serdar Kocbey Burak Cansizoglu Hanifi Ozturk |
| 24 | Mesh Network Studies |
31 days | Sat 03.05.08 | Wed 04.06.08 | |
| 25 | Researching Mesh Networking Algorithms |
7 days | Sat 03.05.08 | Sat 10.05.08 | Serkan Caglar Hanifi Ozturk |
| 26 | Autoamation of Mode Selection of AP Device |
7 days | Sat 03.05.08 | Sat 10.05.08 | Serdar Kocbey Burak Cansizoglu |
| 27 | Implementation of Mesh Middleware |
14 days | Wed 21.05.08 | Wed 04.06.08 | Burak Cansizoglu Serdar Kocbey |
| 28 | Documentation |
10 days | Sat 10.05.08 | Wed 21.05.08 | |
| 29 | Composition of Installation Manual |
5 days | Sat 10.05.08 | Thu 15.05.08 | Serkan Caglar Burak Cansizoglu |
| 30 | Composition of User Manual |
5 days | Thu 15.05.08 | Wed 21.05.08 | Serdar Kocbey Hanifi Ozturk |
| 31 | Final Release Installation Package |
7 days | Wed 21.05.08 | Wed 28.05.08 | |
| 32 | Implementation of Installation Software |
7 days | Wed 21.05.08 | Wed 28.05.08 | Serkan Caglar; Hanifi Ozturk |