Project Start Date: Wed 20.02.08
Project Finish Date: Wed 04.06.08

Gantt Chart of the Schedule (pdf format)

Living Schedule

ID
Name
Duration Start_Date Finish Resource_Names
1
Detailed Database Implementation
2 days Wed 20.02.08 Fri 22.02.08  
2
Defining Entity Relations
1 day Wed 20.02.08 Thu 21.02.08 Hanifi Ozturk
3
Creating New Tables
1 day Wed 20.02.08 Thu 21.02.08 Serkan Caglar
4
Testing the Database
1 day Thu 21.02.08 Fri 22.02.08 Serdar Kocbey
5
Developing HSBS Sentinel Software / Protocol
29 days Wed 20.02.08 Thu 20.03.08  
6
Designing PCB (SP07 (v2.0))
7 days Wed 20.02.08 Wed 27.02.08 Burak Cansizoglu
7
Change the Protocol of Serial Data Reading to AP-400 Driven Mode
10 days Wed 20.02.08 Sat 01.03.08 Serdar Kocbey
8
Bringing Back the Wireless Communication
10 days Wed 20.02.08 Sat 01.03.08 Serkan Caglar
9
Adding AP-400 DHCP Client Property
10 days Wed 20.02.08 Sat 01.03.08 Burak Cansizoglu Serkan Caglar
10
Improving the Algorithm of RS-232 Protocol
10 days Sat 01.03.08 Tue 11.03.08 Hanifi Ozturk Serdar Kocbey
11
Improving the Algorithm of Server to Receive Data Sent from HSBS_Sentinel
19 days Sat 01.03.08 Thu 20.03.08 Serkan Caglar Serdar Kocbey
12
Implementing New Wireless Nodes
7 days Thu 20.03.08 Thu 27.03.08  
13
Assembling new SP07's (v2.0)
4 days Thu 20.03.08 Mon 24.03.08 Hanifi Ozturk
14
Implementing New SP07 Module
4 days Thu 20.03.08 Mon 24.03.08 Hanifi Ozturk
15
SP07 Component Testing
1 day Mon 24.03.08 Tue 25.03.08 Hanifi Ozturk
16
Assembling New HSBS Sentinels
1 day Mon 24.03.08 Tue 25.03.08 Serkan Caglar
17
Testing HSBS_Sentinels (v2.0)
1 day Tue 25.03.08 Wed 26.03.08 Serdar Kocbey
18
Building a Wireless Network and Testing
1 day Wed 26.03.08 Thu 27.03.08 Burak Cansizoglu
19
Implementing the GUI
45 days Tue 18.03.08 Sat 03.05.08  
20
Java / Swing Studies
5 days Tue 18.03.08 Sun 23.03.08 Serkan Caglar Serdar Kocbey Burak Cansizoglu Hanifi Ozturk
21
Implementing Node Monitor
12 days Sun 23.03.08 Fri 04.04.08 Serdar Kocbey Serkan Caglar Burak Cansizoglu
22
Implementing Data Analyzer
14 days Fri 04.04.08 Fri 18.04.08 Serkan Caglar Serdar Kocbey Burak Cansizoglu Hanifi Ozturk
23
Implementing Report Generator
14 days Fri 18.04.08 Sat 03.05.08 Serkan Caglar Serdar Kocbey Burak Cansizoglu Hanifi Ozturk
24
Mesh Network Studies
31 days Sat 03.05.08 Wed 04.06.08  
25
Researching Mesh Networking Algorithms
7 days Sat 03.05.08 Sat 10.05.08 Serkan Caglar Hanifi Ozturk
26
Autoamation of Mode Selection of AP Device
7 days Sat 03.05.08 Sat 10.05.08 Serdar Kocbey Burak Cansizoglu
27
Implementation of Mesh Middleware
14 days Wed 21.05.08 Wed 04.06.08 Burak Cansizoglu Serdar Kocbey
28
Documentation
10 days Sat 10.05.08 Wed 21.05.08  
29
Composition of Installation Manual
5 days Sat 10.05.08 Thu 15.05.08 Serkan Caglar Burak Cansizoglu
30
Composition of User Manual
5 days Thu 15.05.08 Wed 21.05.08 Serdar Kocbey Hanifi Ozturk
31
Final Release Installation Package
7 days Wed 21.05.08 Wed 28.05.08  
32
Implementation of Installation Software
7 days Wed 21.05.08 Wed 28.05.08 Serkan Caglar; Hanifi Ozturk